FIELD: hydraulic engineering, particularly for dam building in severe climate regions.
SUBSTANCE: method for grouting dam including top column and bottom wedge with arranging cemented joint in-between involves opening joint between top column and bottom wedge by creating temperature difference on upper and lower edges of top column due to intensive freezing concrete at upper edge of top column which results in upper column rotation towards upper dam edge and in joint opening; grouting the opened joint. Temperature difference on upper and lower edges column is 15 - 45 C.
EFFECT: promotion of joint grouting, enhanced technological effectiveness of cementing works.
2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR ERECTION OF MASSIVE CONCRETE DAMS IN SEVERE CLIMATIC CONDITIONS | 2008 |
|
RU2384667C1 |
0 |
|
SU513146A1 | |
METHOD OF CONCRETE DAMS ERECTION IN SEVERE CLIMATE | 2002 |
|
RU2243317C2 |
METHOD FOR CONSTRUCTION OF CONCREATE DAM | 0 |
|
SU1629372A1 |
GRAVITY DAM WITH EXPANDED JOINTS | 2011 |
|
RU2495190C2 |
ARCH DAM | 0 |
|
SU1052616A1 |
EARTH DAM | 2013 |
|
RU2550885C2 |
CONCRETE DAM, PROCESS OF ITS ERECTION, METHOD OF ITS EXPLOITATION AND GEAR CONTROLLING TEMPERATURE CONDITION OF CONCRETE BY OUTER FACE OF DAM | 2001 |
|
RU2224067C2 |
METHOD OF MONOLITHING MASSIVE CONCRETE STRUCTURES | 0 |
|
SU723021A1 |
STONE DAM WITH INNER IMPERVIOUS SCREEN MADE OF SOIL-CEMENT-CONCRETE | 2012 |
|
RU2523503C1 |
Authors
Dates
2004-08-10—Published
2003-03-24—Filed