FIELD: hydraulic building, particularly facilities to store industrial waste.
SUBSTANCE: hydraulic fill section includes primary dam formed on base of the section, secondary dams and drainage system arranged in the base. Major part of each secondary dam is located on alleviation beach. Intake means of drainage system are made as drainage branches converging in water intake chamber arranged in the base of the section and spaced from its dam. Water intake chamber is communicated with water supply system of industrial plant by pump and by discharge water channel located in passageway adapted to maintain water intake chamber. At least one secondary dam is provided with apron, which covers alleviation beach. Apron has drain hydraulically communicating with draining branch of drainage system through additional water pass formed in waste arranged in the section. Drain may be formed as drainage belt and provided with drainage pipe. Draining branch may be of tubular type and arranged in trench. If water intake chamber of drainage system is located in spillaway well section water intake chamber may be arranged under the spillaway well and have common body with foundation thereof. In this case discharge water channel may be combined with discharge manifold of spillaway well and maintenance passage is formed inside above manifold. Additional water pass may be movably connected to drainage pipe of drainage belt by tubular member and by connection pipe provided with shutoff device.
EFFECT: increased reliability and reduced costs of above section.
5 cl, 6 dwg
Title | Year | Author | Number |
---|---|---|---|
COMPARTMENT OF SLUDGE POND FOR INDUSTRIAL ENTERPRISES WASTES, METHOD OF ITS DEVELOPMENT AND METHOD OF ITS PRESERVATION | 2009 |
|
RU2385987C1 |
INDUSTRIAL WASTE DISPOSAL AREA | 2004 |
|
RU2261952C1 |
METHOD FOR TIER STOCKING OF GRAIN WASTES INTO SLUDGE POND DRAINED NEAR BASE OF BEACH ZONE | 2009 |
|
RU2410488C1 |
METHOD FOR TIER STOCKING OF GRAIN WASTES INTO SLUDGE POND DRAINED NEAR BASE OF BEACH ZONE | 2009 |
|
RU2413051C1 |
METHOD FOR ERECTION OF SLUDGE POND TIER BUILD-UP DAM | 2009 |
|
RU2392377C1 |
METHOD FOR TIER STOCKING OF GRAIN WASTES INTO SLUDGE POND | 2009 |
|
RU2384669C1 |
METHOD FOR RECLAMATION OF SLUDGE POND COMPARTMENT FILLED WITH GRAINY WASTES OF INDUSTRIAL ENTERPRISES | 2009 |
|
RU2396430C1 |
METHOD FOR STOCKING OF GRANULAR WASTE IN SLUDGE POND SECTION AND INTO BODY OF CONSERVATION OVER SECTION | 2009 |
|
RU2382847C1 |
GULLY TWO-STAGE SLURRY DUMP FOR GRANULAR INDUSTRIAL WASTE | 2004 |
|
RU2275458C1 |
HYDRAULIC-MINE DUMP OF INDUSTRIAL WASTE | 2003 |
|
RU2252295C2 |
Authors
Dates
2005-10-20—Published
2004-02-09—Filed