FIELD: power industry, particularly to repair overhead transmission lines, namely to replace damaged poles by new quickly-assembled ones.
SUBSTANCE: overhead transmission line pole comprises at least one free-standing post with cross-arms connected thereto. Post is composed of telescopically butt-joined conical sections in post height direction. The sections are connected by inserting narrow end of one conical section in wide end of another one with predetermined force. Butt-join length lj of pole sections to be connected is selected from (1.75÷1.85)×dsj. Section taper is within (0.015÷0.035). Force N necessary for prior telescopic section butt-joint compression is calculated from the following equation: N=5.0×Q×lj/dsj, where Q is crosscutting force, kgf, lj - section joint length, cm, dsj is mean cross-sectional diameter of pole sections to be connected with each other in section joint area, cm.
EFFECT: increased operational reliability of overhead transmission line poles, decreased maintenance time and elimination of temporary pole construction.
1 tbl, 6 dwg
Title | Year | Author | Number |
---|---|---|---|
SUPPORT FROM TWISTED BAND FOR SUSPENSION OF WIRES OF POWER TRANSMISSION LINES AND METHOD FOR ITS ERECTION | 2009 |
|
RU2418930C2 |
TEMPORARY QUICK-MOUNTING AND DISMOUNTING SUPPORT OF OVERHEAD TRANSMISSION LINE PER 35-110 Kv | 2013 |
|
RU2539042C1 |
POWER TRANSMISSION LINE SUPPORT | 0 |
|
SU1059106A1 |
POWER TRANSMISSION LINE SUPPORT | 0 |
|
SU1010240A1 |
THREE-PHASE POWER TRANSMISSION LINE SUPPORT | 0 |
|
SU941523A1 |
SUPPORT WITH DOUBLE SHELL FROM TWISTED TAPE FOR SUSPENSION OF POWER TRANSMISSION LINE WIRES | 2009 |
|
RU2501924C2 |
SINGLE-POST STAND-ALONE SUPPORT OF POWER TRANSMISSION LINE WITH CROSS BRACES | 2011 |
|
RU2456422C1 |
POWER LINE SUPPORT | 0 |
|
SU1573117A1 |
TWO-CHAIN INTERMEDIATE SUPPORT AND OVERHEAD LINE WITH SUCH SUPPORT | 2017 |
|
RU2667945C1 |
FREE-STANDING SINGLE-STAND POWER TRANSMISSION POLE | 2004 |
|
RU2256758C1 |
Authors
Dates
2007-09-27—Published
2006-01-19—Filed