FIELD: civil engineering. SUBSTANCE: before installing the formwork the method involves securing nonremovable retainers on floors and vertical structures along the outline of the wall being erected and within the limits of its thickness, said retainers coming out to the face surfaces of the wall. Erection of walls is started from peripheral fragments, installing opposite formwork panels close to retainers and joining them by nonremovable embedded elements. Formwork is filled with concrete mix through pipe union located on formwork panel. When reinstalling the formwork the panels are disposed on concrete section with overlap. On the upper layer the panels are pressed against floor via flexible sealing spacers provided with drain channels. The moment of complete filling of the entire formwork cavity is determined by the discharge of surplus concrete mix. EFFECT: higher efficiency.
Title | Year | Author | Number |
---|---|---|---|
METHOD OF MONOLITHIC BUILDING ERECTION AND MOVABLE FRAMEWORK FOR ITS REALIZATION | 1993 |
|
RU2078884C1 |
HOUSE-BUILDING COMBINE | 1995 |
|
RU2087650C1 |
APPARATUS FOR ERECTING FERROCONCRETE CYLINDRICAL TANK | 0 |
|
SU1350296A1 |
METHOD OF RECONSTRUCTION OF BUILDINGS AND STRUCTURES | 2023 |
|
RU2820548C1 |
METHOD FOR ERECTION OF MONOLITHIC BUILDINGS AND SET OF EXTENDING, DISPLACEABLE, TUNNEL-SHAPE SHUTTERING FOR REALIZATION OF METHOD | 1997 |
|
RU2119026C1 |
STATIONARY FALSEWORK, METHOD FOR ASSEMBLING THE LATTER AND METHOD FOR CONSTRUCTION OF MONOLITHIC WALLS AND STRUCTURES IN STATIONARY FALSEWORK | 2003 |
|
RU2248433C1 |
CENTERING FOR ERECTING MONOLITH WALLS OF BUILDINGS AND STRUCTURES | 0 |
|
SU1761917A1 |
CLIMBING FORMS | 0 |
|
SU1791596A1 |
METHOD AND APPARATUS FOR FORMING AN OPENING IN SOLID CONCRETE WALL | 0 |
|
SU1456526A1 |
METHOD FOR ERECTION OF CAST-IN-SITU MULTILAYER STRUCTURES OF WALL OR COLUMN TYPE | 1993 |
|
RU2035568C1 |
Authors
Dates
1994-12-15—Published
1992-01-14—Filed