FIELD: hydraulic engineering, particularly building bases and foundations, namely bridge piers, in water.
SUBSTANCE: method involves monitoring water obstacle in support building place, including investigating water parameters, recording water level in the course of year, determining floor shape, investigating floor ground, influence of outer disturbing forces and calculating weight and dimensions of support foundation case on the base of above parameters; producing hollow case with several cavities; moving case to installation place; submerging case in water; pacing thereof on floor; fixing case by piles and smoothing floor. Case submerging and placing operations are performed simultaneously with stabilizing vertical case position by performing control and filling of corresponding cavities. Bottom smoothing process is carried out by forcing artificial material, such as concrete layers with crushed stone interlayers, under case bottom. During case placing case is secured by blades built in case bottom and by piles inserted in cavities. Correspondence between case weight, number of blades, head resistance and side friction thereof for particular ground is determined to provide case stability on ground. Upper edge of submerged case is located above maximum possible water wave height. Rock fill is formed around underwater case part.
EFFECT: reduced time of support erection, increased reliability and stability, safety and service life, reduced labor inputs, possibility to erect supports in Arctic basin.
3 cl 1 ex
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR INSTALLATION OF MARINE STATIONARY PLATFORM WITH FLAT BOTTOM AND MARINE STATIONARY PLATFORM | 1993 |
|
RU2057845C1 |
METHOD FOR FORMATION OF CLOSED SECTION OF WATER AREA BOTTOM WITH POSSIBILITY OF ITS DRYING AND SYSTEM, WHICH REALISES IT | 2008 |
|
RU2382142C2 |
ICE RESISTANT DRILLING COMPLEX FOR SHALLOW CONTINENTAL SHELF DEVELOPMENT | 2008 |
|
RU2382849C1 |
ENCLOSURE | 1992 |
|
RU2040632C1 |
FOUNDATION OF FLOATING MASSIF INSTALLED ONTO BASE BY FLOAT-ON METHOD | 2011 |
|
RU2473743C2 |
METHOD FOR CONSTRUCTING BRIDGE SUPPORT IN WATER AREA | 2023 |
|
RU2809049C1 |
ENCLOSURE STRUCTURE | 0 |
|
SU1373750A1 |
METHOD OF BRIDGE BUILDING OVER WATER BODY | 2004 |
|
RU2237123C1 |
FLOATING FACTORY CAISSON | 0 |
|
SU1188249A1 |
APPARATUS FOR CONSTRUCTING BRIDGE PIER FOUNDATION | 0 |
|
SU992658A1 |
Authors
Dates
2005-02-10—Published
2003-05-06—Filed