FIELD: construction.
SUBSTANCE: pile comprises reinforcement frame from longitudinal reinforcement rods. On side surface of pile there are channels arranged for discharge of injected mortar through steel pipe, besides upper end of pipe is brought outside above soil level. In place of one or several longitudinal reinforcement rods there are one or several steel pipes arranged accordingly. Each pipe has several holes arranged in various levels of pipes for discharge of injected mortar through channels. Lower ends of pipes are closed tightly inside pile. Diametres of pipes are preferably equal to diametres of reinforcement rods.
EFFECT: increased bearing capacity and strength of pile, reduced labour intensiveness.
2 cl, 3 dwg
Title | Year | Author | Number |
---|---|---|---|
PILE | 2015 |
|
RU2594499C1 |
DRIVEN REINFORCED CONCRETE PILE FOR CHEMICAL FIXATION OF LOOSE SANDS AND METHOD TO FIX SOIL SURROUNDING PILE BODY | 2011 |
|
RU2492293C2 |
PIPE CONCRETE PILE WITH REINFORCED BASE AND METHOD OF ITS ERECTION | 2011 |
|
RU2492294C1 |
METHOD FOR CONSTRUCTION OF INJECTION PILE | 2014 |
|
RU2550620C1 |
METHOD OF ARRANGING INJECTION PILE | 2016 |
|
RU2637002C1 |
METHOD AND DEVICE FOR LOOSE FOUNDATION BASE CONSOLIDATION BY DIRECTED HORIZONTAL PATTERN HYDRAULIC FRACTURING | 2005 |
|
RU2305153C2 |
PILE AND METHOD OF ITS ERECTION | 2013 |
|
RU2528331C1 |
METHOD FOR REINFORCEMENT OF PILE FOUNDATION | 2019 |
|
RU2728052C1 |
METHOD FOR REINFORCEMENT OF PILE FOUNDATION | 2019 |
|
RU2722901C1 |
METHOD OF CONSTRUCTING AN UNDERWATER FOUNDATION | 0 |
|
SU947292A1 |
Authors
Dates
2010-05-20—Published
2008-10-24—Filed