FIELD: electricity.
SUBSTANCE: method is based on measurement of leakage current from auxiliary source of measuring voltage in the form of periodic sequence of pulses; measurement of leakage current I1 in time range T<t≤2T and leakage current I2 in range 3T<t≤4T by integration of voltage drop on reference resistance over a period of supply mains, calculation of insulation resistance by formula recording of n last values of insulation resistance; calculation as per these values of expected values of insulation resistance in the current measurement range re and further range comparison of values rins, re, with allowable range R0 and in case rins<R0; re<R0 disconnection of electrical equipment; in case rins<R0; re>R0 repeated comparison in the next range and in case of repetition of the case rins<R0 the disconnection of electrical equipment.
EFFECT: increasing quick action of monitoring of insulation and reliability of protection of electrical equipment.
4 dwg
Authors
Dates
2011-12-20—Published
2009-11-20—Filed