FIELD: construction.
SUBSTANCE: sludge pond of industrial enterprises wastes comprises the primary banding dam. The dam is arranged on the sludge pond base and forms its first tier. A drainage layer equipped with a drainage pipe is arranged along the dam. The secondary build-up dams are placed on a silted beach and form subsequent layers of the sludge pond. On the surface of each silted beach of the tier prior to erection of another secondary dam there are longitudinal and transverse drainage tapes arranged. Vertical drains are provided in tiers in the form of wells. Drains connect longitudinal and transverse drainage tapes to each other and the drainage layer.
EFFECT: single space drainage system efficiently dehydrates silted wastes and increases strength of silted massif.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
INDUSTRIAL WASTE DISPOSAL AREA | 2004 |
|
RU2261952C1 |
COMPARTMENT OF SLUDGE POND OF INDUSTRIAL ENTERPRISES WASTES | 2009 |
|
RU2385988C1 |
HYDRAULIC FILL SECTION FOR INDUSTRIAL WASTE STORAGE | 2004 |
|
RU2262566C1 |
METHOD FOR ERECTION OF SLUDGE POND TIER BUILD-UP DAM | 2009 |
|
RU2392377C1 |
METHOD FOR STOCKING OF GRANULAR WASTE IN SLUDGE POND SECTION AND INTO BODY OF CONSERVATION OVER SECTION | 2009 |
|
RU2382847C1 |
METHOD FOR TIER STOCKING OF GRAIN WASTES INTO SLUDGE POND DRAINED NEAR BASE OF BEACH ZONE | 2009 |
|
RU2410488C1 |
METHOD FOR TIER STOCKING OF GRAIN WASTES INTO SLUDGE POND | 2009 |
|
RU2384669C1 |
METHOD FOR TIER STOCKING OF GRAIN WASTES INTO SLUDGE POND DRAINED NEAR BASE OF BEACH ZONE | 2009 |
|
RU2413051C1 |
COMPARTMENT OF SLUDGE POND FOR INDUSTRIAL ENTERPRISES WASTES, METHOD OF ITS DEVELOPMENT AND METHOD OF ITS PRESERVATION | 2009 |
|
RU2385987C1 |
FLOOD-PLAIN SLUDGE POND FOR INDUSTRIAL WASTE | 2004 |
|
RU2275457C2 |
Authors
Dates
2012-01-20—Published
2010-08-24—Filed