FIELD: mining.
SUBSTANCE: method involves development of ore resources, which is performed in two stages. Producing block is divided into ore body falling sections consisting of two primary chambers as to the spread and one secondary chamber consisting of inter-chamber chain pillar and bottoms of primary chambers. Protective pillars are left between blocks. At the first development stage there excavated are primary chambers as to spread to the height of up to 8 m with one working face using self-propelled vehicles and roof and walls of primary chambers and roof above inter-chamber pillar are fixed by installing anchors with mesh. At the second stage there extracted are resources of inter-chamber chain pillars and bottoms of primary chambers to drilling and delivery working-outs between protective chain pillars with width of 2.5-3 m, which are left between sections.
EFFECT: invention allows improving development efficiency, increasing ore production and reducing losses and impoverishment.
2 cl, 5 dwg
Title | Year | Author | Number |
---|---|---|---|
PILLAR WORKING METHOD | 0 |
|
SU1793053A1 |
METHOD FOR DEVELOPMENT OF INCLINED ORE BODIES OF MEDIUM WIDTH | 2016 |
|
RU2632615C1 |
DEVELOPMENT METHOD OF THICK STEEPLY DIPPING ORE BODIES | 2012 |
|
RU2502872C1 |
METHOD OF MINING STEEP SLOPING ORE BODIES | 0 |
|
SU720161A1 |
METHOD FOR WORKING INCLINED ORE OBSTRUCTIONS | 0 |
|
SU1661422A1 |
METHOD OF DEVELOPMENT OF INCLINED ORE DEPOSITS IN RANGE OF BEDDING ANGLES 15-35 DEGREES AND THICKNESS OF ORE BODIES 15-30 METERS WITH CAVING OF ORE AND SURROUNDING ROCKS | 2014 |
|
RU2563857C1 |
METHOD FOR DEVELOPING HORIZONTAL AND LOWER ORE BODIES OF AVERAGE CAPACITY | 2017 |
|
RU2642193C1 |
METHOD OF WORKING STEEP ORE BODIES | 0 |
|
SU1051286A1 |
DEVELOPMENT METHOD OF ORE DEPOSITS WITH BLOCK CAVING SYSTEM WITH ACTIVE FLEXIBLE SEPARATING COVERING | 2009 |
|
RU2426881C1 |
METHOD FOR UNDERGROUND MINING OF STEEPLY DIPPING THICK ORE BODIES | 2021 |
|
RU2757883C1 |
Authors
Dates
2013-01-20—Published
2011-09-19—Filed