FIELD: oil and gas industry.
SUBSTANCE: corrosion inhibitor is dosed before supplying to pumps randomly pumping off wells from tanks as they are filled. After the tank is filled, the oil and water production is automatically pumped off with a pump, wherein the corrosion inhibitor is dosed into an inlet header of the pump for pumping off the well production with the dosing pump. The dosing pump is started up automatically and synchronised with the start-up of the pump for pumping off the well production. The dosing pump is stopped automatically once the watercut of the received production is reduced to 30%. To control the watercut of the received well production, an on-line instrument measuring the water content is installed on the flow oil-pipe line.
EFFECT: reduced consumption of the corrosion inhibitor and improved corrosion protection effect.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
TRANSPORTATION METHOD OF HIGHLY WATER-FLOODED PRODUCT OF OIL DEPOSIT WELLS | 2011 |
|
RU2446317C1 |
METHOD OF OPERATING FLOODED WELLS AND SYSTEM THEREFOR | 2015 |
|
RU2601685C1 |
METHOD OF BATCHING REAGENT-DEMULSIFIER | 2006 |
|
RU2307977C1 |
OIL EXTRACTIVE DEVICE | 2004 |
|
RU2244116C1 |
PLANT FOR TREATMENT OF HEAVY ASPHALT-RESINOUS OIL | 2000 |
|
RU2164435C1 |
METHOD AND DEVICE FOR WELLHEAD STREAM TRANSPORT | 0 |
|
SU1662609A1 |
OIL FIELD PRODUCTION GATHERING SYSTEM | 2000 |
|
RU2159892C1 |
CORROSION PROTECTION METHOD FOR PIPELINES OF WATER-CUT OIL COLLECTING SYSTEM | 2012 |
|
RU2496915C1 |
METHOD FOR SUPPLYING LIQUID CHEMICAL REAGENTS | 2015 |
|
RU2572873C1 |
METHOD FOR BATCHING OF REAGENTS | 2004 |
|
RU2261397C1 |
Authors
Dates
2013-09-20—Published
2012-09-19—Filed