ERECTION METHOD OF PILE OF SHALLOW EMBEDDING Russian patent published in 2014 - IPC E02D5/30 

Abstract RU 2510441 C1

FIELD: construction.

SUBSTANCE: erection method of a pile of shallow embedding involves making of an initial well and installation of a pile shaft into it. The pile shaft is composed of a single steel pipe or it is provided with a telescopic configuration using steel pipes of large diameter with smooth transitions from one section of the shaft to the other so that length l2 of the second pipe is taken at the interval of 1/3 to 1/10 of total pile length L, and in case the third pipe is used, which comprises the pile shaft, its length l3=l2-l2' (where l2' - length of shortened second pipe) is taken at the interval of 1/6 to 1/20 of total pile length L. The lower end of the shaft is equipped with a flat steel bearing plate having the shape of a polygon, a square, a round, a ring, or the bearing plate is made in the form of a grid from a metal profile. The pile shaft is located in the centre of the initial well, the free space of which is filled to depth l2 or l2'+l3 with large, average and small fragmentary material, for example crushed stone, and the above lying volume of the well is filled with wet quartz sand mixed with soil extracted during development of the initial well with further compacting of filler material. The cavity of the shaft itself is left hollow or filled with concrete mixture after or without any introduction to it of a reinforcement cage with vibratory mechanisms involved for normative compacting of concrete.

EFFECT: improving carrying capacity of pile foundations; ensuring environmental security; reducing material consumption.

6 cl, 4 dwg

Similar patents RU2510441C1

Title Year Author Number
DRILLING-AND-DRIVING METHOD FOR PILE FOUNDATION ERECTION IN PERMAFROST GROUND 2006
  • Minkin Mark Abramovich
  • Dashkov Aleksandr Grigor'Evich
  • Filippov Oleg Grigor'Evich
  • Suvorin Aleksej Vasil'Evich
  • Vasilenko Sergej Ivanovich
  • Kolchanov Igor' Vital'Evich
  • Osokin Aleksej Borisovich
  • Popov Aleksandr Petrovich
RU2320821C1
PILE FOUNDATION FOR ARRANGEMENT OF SUPPORTS OF OVERHEAD POWER TRANSMISSION LINE 2014
  • Revel'-Muroz Pavel Aleksandrovich
  • Smirnov Nikolaj Vladimirovich
  • Kumallagov Vitalij Aleksandrovich
  • Semin Evgenij Evgen'Evich
  • Ivakin Aleksandr Vladimirovich
  • Bogatenkov Jurij Vasil'Evich
RU2556588C1
GROUND ANCHOR OR DRILLING PILE AND MANUFACTURING METHOD OF GROUND ANCHOR OR DRILLING PILE 2013
  • Eremin Valerij Jakovlevich
  • Molchanov Kirill Dmitrievich
  • Siguta Jurij Vasil'Evich
  • Fedorovskij Viktor Grigor'Evich
RU2543842C1
CAST-IN-PLACE PILE MANUFACTURING METHOD AND A DEVICE FOR ITS IMPLEMENTATION 2017
  • Borozenets Leonid Mikhajlovich
  • Ushakova Ekaterina Andreevna
RU2679172C1
PILE AND ITS ERECTION METHOD 2013
  • Veselov Aleksandr Vasil'Evich
  • Permjakov Mikhail Borisovich
  • Permjakova Anastasija Mikhajlovna
RU2535556C1
ARRANGEMENT METHOD OF SUPPORTS OF OVERHEAD POWER TRANSMISSION LINES ON PERMANENTLY FROZEN SOILS 2014
  • Revel'-Muroz Pavel Aleksandrovich
  • Smirnov Nikolaj Vladimirovich
  • Kumallagov Vitalij Aleksandrovich
  • Semin Evgenij Evgen'Evich
  • Ivakin Aleksandr Vladimirovich
  • Bogatenkov Jurij Vasil'Evich
  • Zotov Mikhail Jur'Evich
RU2556589C1
METHOD TO RECOVER CONTACT LAYER "FOUNDATION - SOIL BASE" 2015
  • Pronozin Jakov Aleksandrovich
  • Stepanov Maksim Andreevich
  • Volosjuk Denis Viktorovich
RU2572477C1
METHOD OF PILE DRIVE DEVICE 2014
  • Krutov Vladimir Ivanovich
  • Kovalev Aleksandr Semenovich
  • Kovalev Vladimir Aleksandrovich
RU2601630C2
METHOD FOR BUILDING CAST-IN-PLACE PILES AND FORTIFYING THEIR BASES 1998
  • Smirnov A.Ju.
  • Beda V.I.
  • Koroteev Ju.F.
  • Kritsberg L.V.
  • Panin I.A.
  • Khodorov V.G.
RU2139975C1
METHOD FOR BORED INJECTION PILE ERECTION 2003
  • Grin'Ko S.G.
  • Kovalev S.V.
  • Kozakov Ju.N.
  • Bulankin N.F.
RU2260093C2

RU 2 510 441 C1

Authors

Leont'Ev Aleksandr Grigor'Evich

Dates

2014-03-27Published

2012-08-07Filed