FIELD: construction.
SUBSTANCE: manufacturing method of the ground anchor or drilling pile includes formation of the hole in dispersed soil, filling it with hardening plastic material, soil compaction, surrounding the shaft of the pile to be manufactured or anchor root, discretely with formation of dynamic and / or static influence of broadening, which is formed by compaction and partial displacement of soil in each broadening, so that the stress-strain state of the soil adjacent to the broadening has reached the value of the stress-strain state of the soil at the base of the pile, in this case the maximum distance l between the centres of broadenings along the hole axis is determined by the reduced dependence.
EFFECT: provision of specific load-bearing capacity of the soil along the anchor root, reduction of consumption of cured material, increase of productivity in the manufacture of bored piles and ground anchors at the same time with increase of their load-carrying capacity due to the effective use of the bearing capacity of the soil.
4 cl, 5 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF CONSTRUCTING GROUND ANCHOR AND GROUND ANCHOR ITSELF | 1997 |
|
RU2131495C1 |
METHOD OF DRILLED PILE MANUFACTURING | 2009 |
|
RU2389849C1 |
METHOD OF PILE PRODUCTION | 2017 |
|
RU2654097C1 |
MANUFACTURING METHOD OF ASSEMBLY ATTACHING PILE TO AVAILABLE FOUNDATION AT ITS BEING REINFORCED (VERSIONS) | 2008 |
|
RU2385384C1 |
METHOD OF DRILLING INJECTION PILE | 2023 |
|
RU2817842C1 |
REINFORCED CONCRETE DRILLING PILE AND METHOD OF ITS ERECTION | 2016 |
|
RU2657885C2 |
METHOD OF ARRANGEMENT OF ROOT PILE WITH CONTROLLED WIDENING | 2015 |
|
RU2614131C1 |
EARTH PILE AND METHOD FOR MANUFACTURING EARTH PILES | 2021 |
|
RU2763656C1 |
METHOD OF GROUND ANCHOR INSTALLATION AND ASSOCIATED DEVICE | 2006 |
|
RU2344230C2 |
METHOD OF PRODUCTION OF CAST-IN-PLACE PILE | 1994 |
|
RU2100525C1 |
Authors
Dates
2015-03-10—Published
2013-11-29—Filed