FIELD: production of conversion tubes of low-ductility steel with boron content 1.3 - 1.8%.
SUBSTANCE: method comprises steps of drilling ingots of electroslag refining, heating them till ductility temperature, piercing in piercing mill for making sleeves; rolling sleeves in pilger mill to tube-blanks, cooling, repairing, cutting tube-blanks by two blanks, heating them up to ductility temperature, piercing-rolling in piercing mill and rolling conversion tubes in pilger mill. Ingots of electroslag refining with diameter 460 - 480 mm are drilled from their bottom end along length L = H - B, where H - height of ingot, mm; B - under-drilled part of ingot equal to 100 - 120 mm. Then ingots are soaked at temperature 450 - 500°C on grates of heating furnace without tilting for 90 - 120 min; heated till 800 - 850° C at rate 1.8 - 2.0°C/min; then heated up to ductility temperature 1050 - 1090°C at rate 2.1 - 2.2°C/min at tilting in 15 - 20 min and soaked at such temperature for 70 - 80 min at tilting by angle about 180° in 10 -15 min.
EFFECT: lowered content of waste material, improved quality of conversion tubes, reduced cost of ready product.
5 cl, 1 tbl
Title | Year | Author | Number |
---|---|---|---|
METHOD OF CONVERSION PIPE MANUFACTURING IN PIPE ROLLING PLANTS WITH PILGER MILLS OF LOW-ELASTICITY STEEL WITH BORON CONTENT OF 1,3-1,8% | 2006 |
|
RU2334571C2 |
PRODUCTION OF HEXAGONAL PIPE BILLETS FOR COMPACT STORAGE AND TRANSPORTATION OF USED NUCLEAR FUEL FROM LOW-DUCTILE STEEL WITH BORON CONTENT OF 1,3-3,5% | 2013 |
|
RU2541212C2 |
METHOD FOR PRODUCING CONVERSION TUBES OF LOW DUCTILE BORON STEEL | 2006 |
|
RU2297893C1 |
METHOD OF PRODUCING OF TUBE STOCK SIZED TO 290X12 MM TO SPECS 8-16 | 2012 |
|
RU2511199C1 |
METHOD FOR PRODUCING INGOT-BLANKS BY ELECTROSLAG REFINING OF LOW-DUCTILE STEEL CONTAINING BORON AND FOR ROLLING TUBES OF SUCH BLANKS IN TUBE ROLLING PLANTS WITH PILGER MILLS FOR FURTHER CONVERSION OF TUBES TO HEXAHEDRAL TUBE-BLANKS FOR COMPACTED STORAGE OF WASTE NUCLEAR FUEL | 2006 |
|
RU2317865C2 |
METHOD FOR PRODUCTION OF HEXAGONAL PIPE BILLETS OF INCREASED ACCURACY WITH SIZE 257+1.5/-1.0×6±1.0×4300+80/-20 mm FROM LOW-PLASTICITY STEEL “04Х14Т3Р1Ф” WITH BORON CONTENT FROM 1.3 TO 1.8% FOR COMPACTED STORAGE IN COOLING PONDS OF NUCLEAR POWER PLANTS AND TRANSPORTATION OF SPENT NUCLEAR FUEL | 2024 |
|
RU2836287C1 |
METHOD FOR PRODUCTION OF HEXAGONAL PIPE BILLETS WITH SIZE 257+2.0/-3.0×6+2.0/-1.0×4300+80/-20 mm FROM LOW-PLASTICITY STEEL GRADE “04Х14Т3Р1Ф” WITH BORON CONTENT FROM 1.3 TO 1.8% FOR COMPACTED STORAGE IN COOLING POND OF NUCLEAR POWER PLANTS AND TRANSPORTATION OF SPENT NUCLEAR FUEL | 2024 |
|
RU2836253C1 |
METHOD OF PRODUCTION OF REROLLED PIPES | 2018 |
|
RU2696801C1 |
PRODUCTION OF REROLLED 292×12 mm PIPES AT PRU 8-16" WITH PILGER MILLS FROM ESR INGOTS-BILLETS OF LOW-DUCTILITY "04Х14ТЗР1Ф-Ш"- AND "04Х14Т5Р2Ф-Ш"-GRADE STEELS WITH BORON CONTENT OF 1,3-3,5% FOR FABRICATION OF HEXAGONAL TURNKEY PIPE BILLETS SIZED TO 257+2,0/-3,0×6+2,0/-1,0×4300+80/-30 mm FOR STORAGE AT RACKS OF NUCLEAR POWER STATION USED FUEL COOLING POND AND ITS TRANSPORTATION | 2013 |
|
RU2550033C2 |
METHOD FOR PRODUCTION OF HEXAGONAL PIPE BILLETS OF INCREASED ACCURACY WITH SIZE 257+1.5/-1.0×6±1.0×4300+80/-20 mm FROM LOW-PLASTICITY STEEL “04Х14Т5Р2Ф” WITH BORON CONTENT FROM 2.01 TO 3.5% FOR COMPACTED STORAGE IN COOLING PONDS OF NUCLEAR POWER PLANTS AND TRANSPORTATION OF SPENT NUCLEAR FUEL | 2024 |
|
RU2836256C1 |
Authors
Dates
2005-07-10—Published
2003-06-23—Filed