FIELD: building, particularly for erecting pile foundations of separate tower, mast and other structures.
SUBSTANCE: method involves driving pile in ground by applying dynamic force to the pile by means of pile driver; compacting ground near the pile by applying impacts to the ground by means of heavy rammer at terminal pile driving stage simultaneously with acting on pile with pile driver.
EFFECT: increased dynamic pile-capacity and operational efficiency.
6 dwg, 4 ex
Title | Year | Author | Number |
---|---|---|---|
METHOD OF SLAB-PILE FOUNDATION ERECTION | 2006 |
|
RU2328576C1 |
PIPE CONCRETE PILE WITH REINFORCED BASE AND METHOD OF ITS ERECTION | 2011 |
|
RU2492294C1 |
METHOD TO PRODUCE WELLS IN SOIL FOR ERECTION OF FILLING PILE AND DEVICE FOR ITS REALISATION | 2011 |
|
RU2475593C2 |
METHOD OF PILE DRIVE DEVICE | 2014 |
|
RU2601630C2 |
METHOD OF PILE PRODUCTION | 2017 |
|
RU2654097C1 |
DEVICE FOR COMPACTION OF SOIL IN BOTTOMHOLE | 2008 |
|
RU2401909C2 |
"KVASHA" PILE AND METHOD FOR DEEPENING IN SOIL | 1991 |
|
RU2047689C1 |
METHOD OF CONSTRUCTING A FOUNDATION | 0 |
|
SU1193239A1 |
METHOD FOR PILE CONSTRUCTION IN MACRO-POROUS SOILS | 2020 |
|
RU2753295C1 |
DRIVE PILE DEVICE IN PUNCHED WELL WITH WIDER BASE | 2014 |
|
RU2582530C2 |
Authors
Dates
2005-08-10—Published
2003-07-15—Filed