FIELD: well building, particularly to retain reservoir properties of productive bed during well protection against contaminating and clogging action of filtrate.
SUBSTANCE: well casing method involves lowering production string in well; washing-out clay coating with buffer liquid; creating protective shield made as impervious cement coating of chemical agent modified cement mortar, wherein polyvinyl acetate reagent taken in amount of 0.25-0.5% by weight of cement mass is used as the chemical agent for cement modification. Above modification is performed by solving polyvinyl acetate reagent in water during mixing water preparation with the use of antifoaming agent taken in amount of 10% by volume of polyvinyl acetate reagent mass. The chemical agent modified cement mortar is injected in portions. After the first portion injection ordinary cement mortar is supplied. At the end of injection operation the modified cement mortar portion is injected to separate productive section beds. At the end of well casing operation the first portion of modified cement mortar is forced to day surface.
EFFECT: possibility to retain reservoir properties of the bed, increased technological effectiveness of well casing material preparation and usage.
2 cl, 1 tbl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
WELL CEMENTING METHOD | 2008 |
|
RU2382172C1 |
METHOD FOR WATER INFLOW ISOLATION IN NON-CASED HORIZONTAL PART OF PRODUCTION WELL BORE | 2004 |
|
RU2273722C2 |
CASING STRING CEMENTING METHOD IN WELL | 2019 |
|
RU2720025C1 |
WELL CEMENTING METHOD | 2022 |
|
RU2797167C1 |
METHOD OF CEMENTING CASING STRING IN WELL | 2023 |
|
RU2823955C1 |
METHOD FOR LIMITING INFLUX OF WATER INTO PRODUCTION WELL | 2009 |
|
RU2392419C1 |
METHOD OF WELL'S HORIZONTAL BOREHOLE PART REPAIR INSULATION WORKS | 2008 |
|
RU2379472C1 |
RESERVOIR SELECTIVE SEALING METHOD AT WELL CASING STRING FIRST STAGE CEMENTING | 2008 |
|
RU2379475C1 |
ISOLATION METHOD FOR BOREHOLE ANNULUS CIRCULATION OF SUPERIOR NON PERFORATED AQUIFER IN DOWNSTREAM PERFORATED OIL-BEARING LAYER | 2015 |
|
RU2584256C1 |
METHOD OF CEMENTING CASING STRING | 2015 |
|
RU2605856C1 |
Authors
Dates
2006-01-20—Published
2003-07-30—Filed