FIELD: construction.
SUBSTANCE: method of erection consists that casing is mounted between flooring slabs and columns, having laid preliminary of shuttering panels executed in a form of plywood strips on temporary skywalks and racks on which then floor slabs are laid in design position. Channels of contact seams formed between slabs are closed from below by plywood strips with holes between which longitudinal bars are placed. Slinging turning joints are executed in a form of wire passed through holes in plywood strips round a longitudinal bar; wire ends are passed through a channel of contact seam and are fixed accordingly on each cross-section bar by their tommy screw among them. Warming up is made due to power supplies feed on wire tommy screws.
EFFECT: possibility of continuous operation and crack formation exception at carrying out of a laid concrete mix steam treatment.
7 cl, 4 dwg, 2 ex
Title | Year | Author | Number |
---|---|---|---|
METHOD OF CONSTRUCTING FRAMEWORK WITHOUT LONGITUDINAL GIRDER | 2006 |
|
RU2325487C1 |
METHOD OF BUTT JOINTING OF CEILING PLATES WITH COLUMN AND DEVICE FOR ITS IMPLEMENTATION | 2007 |
|
RU2334060C1 |
BUILDING SKELETON ERECTION METHOD | 1993 |
|
RU2032047C1 |
STRUCTURE OF PRECAST FLOOR AND METHOD OF ITS ERECTION | 2008 |
|
RU2378461C1 |
LARGE-BLOCK BUILDING AND METHOD TO MANUFACTURE ITEMS FOR ITS ERECTION | 2012 |
|
RU2498024C1 |
METHOD OF MONOLITHIC BUILDING ERECTION AND MOVABLE FRAMEWORK FOR ITS REALIZATION | 1993 |
|
RU2078884C1 |
PRE-STRESSED REINFORCED CONCRETE BUILDING SKELETON | 1999 |
|
RU2166032C1 |
METHOD OF ERECTION OF MONOLITHIC AND PREFABRICATED MONOLITHIC FRAMES | 2024 |
|
RU2836225C1 |
DEVICE FOR INDUCTION HEATING OF MONOLITHIC REINFORCED CONCRETE STRUCTURES TO BE CONCRETED | 2016 |
|
RU2633607C1 |
METHOD FOR REINFORCEMENT ROPE TIGHTENING DURING BUILDING ERECTION IN ACCORDANCE WITH INDUSTRIAL ERECTION SYSTEM | 2002 |
|
RU2264506C2 |
Authors
Dates
2008-07-10—Published
2006-10-26—Filed