FIELD: mining.
SUBSTANCE: pit edge includes berm with cross-over for dump trucks of high carrying capacity, which is located in upper part of pit, and berm with cross-over for dump trucks of low carrying capacity, which can overcome high slope, and which is located from surface to horizon of target depth of the pit. Horizontal platform between berm branches for dump trucks of low carrying capacity, which can overcome high slope, is located above horizontal platform before berm end for dump trucks of high carrying capacity. Berm for dump trucks of high carrying capacity is fully occupied throughout the width with tiers of dump of overburden rocks.
EFFECT: improving development efficiency owing to reducing transportation costs of rock mass from lower part of pit and increasing the volume of dump of overburden rocks, which is located on berm with cross-over for dump trucks with high carrying capacity in upper part of pit.
4 dwg
Title | Year | Author | Number |
---|---|---|---|
PIT BORDER | 2007 |
|
RU2353769C2 |
METHOD FOR OPEN DEVELOPMENT OF DEEP-LYING STEEPLY FALLING MINERAL DEPOSITS | 2018 |
|
RU2693798C1 |
METHOD OF OPENING DEEP PITS | 2013 |
|
RU2534305C1 |
OPENCAST WITH TWO CLOSELY LOCATED ORE BODIES DEVELOPMENT METHOD | 2008 |
|
RU2382200C1 |
METHOD OF OPEN-PIT MINING | 1996 |
|
RU2098627C1 |
QUARRY DEVELOPMENT METHOD | 1996 |
|
RU2118456C1 |
METHOD OF OPENCAST MINING OF STEEP ELONGATED MINERAL DEPOSITS | 1999 |
|
RU2171377C2 |
PROCESS OF OPENCAST MINING OF STEEPLY DEEPING STRETCHED-OUT MINERAL DEPOSITS | 2002 |
|
RU2224109C2 |
METHOD FOR OPENCAST STEEP DEPOSIT MINING | 2005 |
|
RU2294434C1 |
METHOD OF OPENCAST MINING OF STEEPLY DIPPING STRETCHED DEPOSITS | 1999 |
|
RU2167297C2 |
Authors
Dates
2011-04-10—Published
2009-10-13—Filed