FIELD: machine building.
SUBSTANCE: combined-cycle gas-plant includes a boiler with fluidised bed under pressure, with a furnace containing a fluidised bed and a cyclone, installed inside the body, gas turbine unit, a steam turbine with a regenerative equipment tract, heat exchangers for cooling of the gases leaving the gas turbine and ash, leaving out boiler, gas treatment unit, the vortex chamber with a device for removing the slag in the liquid state, gas cooler. In parallel with the boiler on the air supply, coal and sorbent the device comprises a gasifier with fluidised bed. A stream of fuel gas leaving the gasifier is divided into two substreams. One substream of the fuel gas is fed for combustion into the vortex chamber. The combustion products of the vortex chamber are cooled in a slag trap beam and a gas cooler, and are cleaned in a ceramic filter and fed into the combustion chamber of a gas turbine. The second substream of combustible gas passes successively cooler gas sulfur cleaner installation, ceramic filter and then enters the combustion chamber of a gas turbine. In the combustion chamber the mixture of combustion products and combustible gas subflow takes place, as well as raising of the temperature of gases produced by burning fuel gas before the gases enter the gas turbine.
EFFECT: safe operation of the installation owing to the use of combustible gas produced in its own cycle, increase of efficiency factor at the cost of raising the temperature of the gases in front of the gas turbine.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
COMBINED-CYCLE PLANT | 2009 |
|
RU2382887C1 |
STEAM GAS PLANT WITH COAL PYROLYSIS | 2009 |
|
RU2387847C1 |
COMBINED ASH CATCHER | 2011 |
|
RU2453770C1 |
METHOD OF AND INSTALLATION FOR THERMAL TREATMENT OF BROWN COAL WITH PRODUCTION OF ELECTRIC ENERGY | 2001 |
|
RU2211927C1 |
STEAM-GAS PLANT FLUIDIZED-BED FURNACE | 0 |
|
SU1758338A1 |
METHOD OF INTERNAL CYCLIC FUEL GASIFICATION AND GENERATION OF ELECTRIC ENERGY, AND PLANT FOR ITS IMPLEMENTATION | 2008 |
|
RU2413750C2 |
GAS-TURBINE PLANT | 2004 |
|
RU2278286C2 |
COMBINATION STEAM-GAS POWER PLANT AND METHOD OF ITS OPERATION | 1998 |
|
RU2124134C1 |
FLUIDIZED-BED FURNACE OF STEAM-GAS PLANT | 0 |
|
SU1758337A1 |
COMBINED CYCLE POWER PLANT AND ITS OPERATING PROCESS | 2001 |
|
RU2245446C2 |
Authors
Dates
2012-07-10—Published
2010-07-26—Filed