FIELD: mining.
SUBSTANCE: method includes well drilling between the surface and roof of isolated underground working, construction of isolating barrier in the isolated underground working in case of emergency situation via pumping of hardening material into the working. Note that the cavity is created in the roof of isolated underground working before the emergency situation. Well drilling is done in geometrical centre of the cavity and supply of hardening material is done till complete cavity filling. Cavity size in direction perpendicular to the working longitudinal axis is taken equal to the width of isolated underground working, and height - equal to the product of half of isolated underground working width by tangent of hardening material spreading angle. Cavity size by the length of isolated underground working is defined by the proportion: lc≤2hc ctgφ, where lc - cavity size by the length of isolated underground working, m; hc - cavity height in the roof of isolated underground working, m; φ - angle of hardening material spreading, degree.
EFFECT: increase of reliability of emergency area isolation at underground fires.
2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR ISOLATION OF EMERGENCY AREA AT COAL BED UNDERGROUND DEVELOPMENT | 2010 |
|
RU2459085C2 |
METHOD OF ISOLATION OF EMERGENCY SECTION OF UNDERGROUND MINE WORKING | 2011 |
|
RU2462596C1 |
METHOD TO ISOLATE EMERGENCY SECTION OF UNDERGROUND MINE | 2011 |
|
RU2471075C1 |
METHOD FOR ISOLATING AND EXTINGUISHING OF UNDERGROUND FIRES IN HARD-TO-REACH SITES OF MINE SHAFTS | 1997 |
|
RU2133830C1 |
PROCESS OF BREAKDOWN SITE ISOLATION | 2003 |
|
RU2328600C2 |
METHOD OF ISOLATION OF EMERGENCY DISTRICT IN UNDERGROUND MINING | 1998 |
|
RU2150585C1 |
PROCESS OF ISOLATION OF FAULTY SECTION THROUGH HOLE FROM SURFACE | 2002 |
|
RU2223404C2 |
METHOD OF ISOLATING EMERGENCY SECTION IN UNDERGROUND WORKING | 1995 |
|
RU2086772C1 |
PROCESSING METHOD OF INSULATION OF MINE WORKING AT THERMAL DEVELOPMENT OF OIL DEPOSITS | 2017 |
|
RU2687725C1 |
MINE CONNECTORS CONSTRUCTION METHOD | 2017 |
|
RU2677186C1 |
Authors
Dates
2012-08-20—Published
2010-12-29—Filed