FIELD: mining.
SUBSTANCE: between sub-levels and compensating gates dividing sub-levels into mining blocks there are furnaces with slope parallel to angle of formation of caved ground in mined area relatively to the line of bed course. Ventilation roadway for ventilating the below sub-level is made after mining and forced falling of the roof at above sub-level, note that above the ventilation roadway there maintained is a protective pillar that temporary prevents rock falling. In below sub-level the roof is controlled by stepped bypassing of caved ground from the above sub-level to bottom-hole area of below sub-level, exposed for allowable passage, note that allowable passage of roof exposure in bottom-hole area of below sub-level and corresponding extended distance between the blocks in comparison to the above sub-level is defined by the expression.
EFFECT: invention allows increasing coal production efficiency.
3 cl, 9 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF UNDER-LEVEL PLASTS' DEVELOPMENT PROCESSING WITH THE BINDING OF THE ESTABLISHED SPACE | 2017 |
|
RU2644185C1 |
METHOD FOR DEVELOPMENT OF STEEP COAL SEAMS OF MEDIUM THICKNESS | 1994 |
|
RU2085738C1 |
PROCEDURE FOR DEVELOPMENT OF STEEPLY PITCHING BEDS OF COAL | 2009 |
|
RU2390633C1 |
METHOD FOR MINING THICK STEEP COAL SEAMS | 1994 |
|
RU2085739C1 |
METHOD OF MINING THICK STEEPLY DIPPING SEAMS WITH FILLING | 0 |
|
SU1710751A1 |
METHOD FOR DEVELOPMENT OF THICK STEEP-DIPPING COAL SEAMS | 1998 |
|
RU2138639C1 |
METHOD FOR EXTRACTION OF MASSIVE STEEP COAL BEDS PRONE TO SPONTANEOUS IGNITION | 2004 |
|
RU2254470C1 |
METHOD FOR MINING STEEP SEAMS | 1997 |
|
RU2123597C1 |
METHOD OF MINING THICK STEEP COAL SEAMS | 1994 |
|
RU2078211C1 |
METHOD FOR MINING THICK STEEPLY DIPPING SEAMS BY HYDRAULIC BREAKING WITH CAST SELF-CEMENTING FILL | 1993 |
|
RU2069752C1 |
Authors
Dates
2013-03-20—Published
2011-09-13—Filed