FIELD: construction.
SUBSTANCE: method of lifting and levelling buildings/constructions involves the installation of injection pipes and the injection of mobile mortar under the building/construction. Injection cuff pipes under the building/construction are installed horizontally in two stages. At the first stage the sandy soil is conditioned, which makes it possible to redistribute the ground material around the injector in a given radius. Injection of the main injection solution in injectable sleeve pipes, in each of which the injection solution is applied repeatedly to create volumetric bodies of the injection material at strictly defined points of the core, is executed in the second stage.
EFFECT: providing the possibility of redistribution of ground material around the injector in a given radius for its subsequent compaction during the injection of injection solution, increasing efficiency of lifting and levelling of constructions.
1 tbl, 1 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR INJECTION FIXATION AND REINFORCEMENT OF BASES OF FOUNDATIONS OF DEFORMED AND RECONSTRUCTED BUILDINGS AND STRUCTURES, CARRIED OUT BY IMPREGNATING WATER-SATURATED SOILS USING LOW-VISCOSITY HIGH-PENETRATING GELLING HARDENING SOLUTION BASED ON SILICA SOL AND ORGANOSILICON COMPOSITIONS | 2024 |
|
RU2824786C1 |
METHOD OF FIXING AND ENHANCING THE CARRYING CAPACITY OF WET FINE GRAIN SOILS OF RUNNING TYPE UNDER BASES AND FOUNDATIONS OF BUILDINGS AND STRUCTURES | 2015 |
|
RU2594495C1 |
METHOD FOR REINFORCEMENT OF PILE FOUNDATION | 2019 |
|
RU2728052C1 |
TILTED BUILDING STRAIGHTENING METHOD | 2004 |
|
RU2275473C1 |
METHOD FOR REDUCING SETTLEMENT OF BUILDINGS DURING CONSTRUCTION OF UNDERGROUND WORKINGS UNDER THEM | 2020 |
|
RU2749003C1 |
METHOD TO CORRECT IRREGULARITIES OF BUILDINGS AND STRUCTURES SUBSIDENCE ON SLAB FOUNDATION | 2011 |
|
RU2468152C1 |
METHOD FOR STRENGTHENING STRUCTURALLY UNSTABLE SOILS WITH KARST FORMATIONS AND/OR WATER-SATURATED SOILS USING MICROPILES AND INJECTORS FOR FORMING MICROPILES | 2022 |
|
RU2795924C2 |
METHOD FOR PRODUCING A CLAY SOIL PILE | 2020 |
|
RU2767469C1 |
METHOD FOR REINFORCEMENT OF PILE FOUNDATION | 2019 |
|
RU2722901C1 |
METHOD FOR PLATE-PILE FOUNDATION CONSTRUCTION | 2016 |
|
RU2616633C1 |
Authors
Dates
2018-02-01—Published
2016-11-08—Filed