METHOD FOR MANUFACTURING A REINFORCED CONCRETE BLOCK ROOM FOR A MOBILE WORKSHOP FOR BLOCK HOUSING CONSTRUCTION Russian patent published in 2023 - IPC E04B1/348 B28B5/00 B28B7/22 

Abstract RU 2794678 C1

FIELD: construction.

SUBSTANCE: invention can be used in the construction of monolithic reinforced concrete structures, namely in the manufacture of three-dimensional elements such as block rooms for ground housing and public construction of buildings and structures, as well as for underground construction under extreme conditions. The method of manufacturing a reinforced concrete block room for a mobile block house-building shop is characterized by the fact that it is carried out by the method of lowering concrete laid in layers. Initially, a formwork stand is equipped in the pit with the dimensions of the block room, for which fixed vertical decks are installed along the perimeter of the pit, consisting of internal and external parts, the distance between which is equal to the thickness of the wall of the block room, a movable horizontal deck fixed on jacks is installed inside the vertical deck located at the bottom of the pit, a fixed horizontal floor deck is installed on top of the pit above the vertical decks. Four rolls of polymer film are movably fixed at the top and bottom of the horizontal floor deck, the edges of the film are fixedly fixed on the horizontal deck, reinforcing cages, consisting of horizontal and vertical meshes, are installed inside the formwork. Before laying the first layer of concrete, the horizontal deck is placed below the upper edge of the inner part of the vertical deck by the thickness of the concrete layer, then reinforcing cages are laid on the horizontal deck and the first layer of concrete is laid into the formwork along the entire perimeter with a concrete pump, then the horizontal deck with the concrete pump located on it is gradually lowered with the first layer of concrete using hydraulic jacks at a speed of 0.8-1 cm/min down to an elevation on the vertical deck equal to the thickness of the layer. Simultaneously with lowering of the first concrete layer, a polymer film is lowered along the vertical deck, and the first layer of concrete is obtained along the entire perimeter of the walls of the block room. After hardening of concrete, the layer is treated with adhesive impregnation from above and reinforcing cages are installed. Then all these steps are repeated for each of the remaining layers of concrete. For the manufacture of the last wall layer of concrete, temporary wooden beams and a polymer film are laid on the horizontal floor deck in the gutters and a horizontal reinforcing cage is installed. The horizontal frame is connected through nodes with the vertical reinforcing frame, then the horizontal concrete layer and the last vertical concrete layer are simultaneously laid on the base of the horizontal floor deck and on the vertical concrete layer, forming a single element. The finished block room is held for 24 hours to gain strength, then it is lifted up with the help of jacks, removed from the formwork and placed on a trolley for transportation.

EFFECT: reduction in labour intensity and a simplification of the procedure for manufacturing a block room.

1 cl, 10 dwg

Similar patents RU2794678C1

Title Year Author Number
METHOD TO FORM REINFORCED CONCRETE STRUCTURES BY MEANS OF DESCENDING CONCRETE 2014
  • Khafizov Tagir Mavlitovich
  • Golovnev Stanislav Georgievich
  • Denisov Sergej Egorovich
  • Khafizov Gleb Tagirovich
RU2566540C1
METHOD FOR CONSTRUCTION OF UNDERGROUND MULTISTOREY BUILDINGS 2015
  • Khafizov Tagir Mavlitovich
  • Bajburin Albert Khalidovich
  • Denisov Sergej Egorovich
  • Khafizov Gleb Tagirovich
RU2604098C1
FIXED FORMWORK SYSTEM FOR LARGE-BLOCK CONSTRUCTION OF BUILDINGS 2019
  • Anpilov Sergej Mikhajlovich
  • Anpilov Mikhail Sergeevich
  • Kitajkin Aleksej Nikolaevich
  • Malinin Sergej Mikhajlovich
  • Murashkin Gennadij Vasilevich
  • Rimshin Vladimir Ivanovich
  • Sakharov Gennadij Stanislavovich
  • Sorochajkin Andrej Nikolaevich
RU2720548C1
STANDARD STRUCTURAL CURB BLOCK 2007
  • Mikhajlov Gennadij Jakovlevich
RU2392394C2
LARGE-BLOCK BUILDING AND METHOD TO MANUFACTURE ITEMS FOR ITS ERECTION 2012
  • Tikhomirov Boris Ivanovich
  • Korshunov Aleksandr Nikolaevich
  • Korolev Sergej Aleksandrovich
RU2498024C1
STRUCTURAL FORMWORK BLOCK FOR OPENINGS 2013
  • Mikhajlov Gennadij Jakovlevich
  • Novikov Aleksandr Viktorovich
RU2525242C1
BUILDINGS AND STRUCTURES WITH BEARING MONOLITHIC REINFORCED CONCRETE STRUCTURES CONSTRUCTION METHOD USING THE REINFORCED CONCRETE WALL PANELS 2018
  • Poselenov Pavel Aleksandrovich
  • Bogdanov Anatolij Anatolevich
  • Ignatenko Aleksandr Ivanovich
RU2678750C1
METHOD OF MULTI-STOREY BUILDING LIGHTENED FLOORS INSTALLATION 2017
  • Anpilov Sergej Mikhajlovich
  • Eryshev Valerij Alekseevich
  • Gajnullin Marat Mansurovich
  • Murashkin Gennadij Vasilevich
  • Murashkin Vasilij Gennadievich
  • Anpilov Mikhail Sergeevich
  • Rimshin Vladimir Ivanovich
  • Sorochajkin Andrej Nikolaevich
  • Kitajkin Aleksej Nikolaevich
RU2652402C1
METHOD FOR MANUFACTURING VOLUMETRIC HOUSING MODULE FOR TRANSFORMER DISTRIBUTION SUBSTATIONS 2019
  • Gorbunov Aleksej Valerevich
RU2691232C1
DEVICE FOR ERECTING LOW-RISE BUILDINGS 0
  • Matskevich Aleksandr Fedorovich
  • Glushchenko Yurij Alekseevich
  • Dubovskij Vladimir Vasilevich
  • Kalistratov Sergej Nikolaevich
SU1744225A1

RU 2 794 678 C1

Authors

Khafizov Tagir Mavlitovich

Baiburin Albert Khalitovich

Denisov Sergei Egorovich

Ovchinnikov Andrei Dmitrievich

Dates

2023-04-24Published

2022-11-21Filed