FIELD: construction.
SUBSTANCE: invention is intended for carrying out work and intermediate storage of materials when performing various tasks during the construction of high-rise monolithic buildings, during the reconstruction of buildings, installation of service walls, installation of windows, in particular, using the system, it is possible to carry out repairs and construction, for example, of bridges, dams, columns, and use both outside and inside the building. The multifunctional lifting system includes at least two support units, on each of which a guide post with a lifting beam is installed and secured perpendicular to them; lifting scaffolds are attached to the latter, while to create stability and eliminate shifts, lifting beams and lifting scaffolds are connected into a spatial system consisting of elements of inventory scaffolds of manual assembly, which are a set of metal multidirectional connections, and a jacking system, where the latter consists of at least two hydraulic cylinders, pivotally connected to a lifting beam and a guide post.
EFFECT: creation of a new principle for lifting systems, which consists of continuous lifting of the building under construction, walls, columns and foundations across the site.
2 cl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
BUILDING CONSTRUCTION COMBINATION MACHINE | 0 |
|
SU972021A1 |
INVENTORY SCAFFOLDS OF MANUAL ASSEMBLY | 2021 |
|
RU2756448C1 |
METHOD FOR JOINING COASTAL AND RIVER PARTS OF FLOATING UNIFIED RAILWAY RIBBON BRIDGE MLZH-VF-VT | 2020 |
|
RU2750370C1 |
SLIDING FORMS FOR CONSTRUCTING STRUCTURES USING REINFORCED BLOCKS | 0 |
|
SU1101532A1 |
SLIDING FORMS | 2012 |
|
RU2495212C1 |
METHOD AND DEVICE FOR CYLINDRICAL RESERVOIR ERECTION BY TOP-DOWN CONSTRUCTION METHOD | 2003 |
|
RU2261313C2 |
SET OF MEMBERS FOR SCAFFOLD OF MANUAL ASSEMBLY | 2002 |
|
RU2199638C1 |
METHOD OF CONSTRUCTING BRIDGE SUPPORT GRILLAGE IN RIVER WATER AREA | 2023 |
|
RU2809068C1 |
METHOD OF MOUNTING IMZH-500 RAILROAD BRIDGE WITH COLLAPSIBLE RAILWAY CANTILEVER CRANE FOR INSTALLATION OF SUPPORT AND SPANS IN ONE PROCESS CYCLE | 2020 |
|
RU2740595C1 |
PLANT FOR DOING FINISHING WORK | 0 |
|
SU1768730A1 |
Authors
Dates
2023-12-05—Published
2023-08-17—Filed