FIELD: mining industry, applicable for slanting of high benches at development of magmatic deposits of mineral resources by open pit.
SUBSTANCE: the method includes drilling of contour holes for formation of a screening peephole, buffer and breaking holes to a depth corresponding to the height of one working subbench with a redrill, the middle row of breaking holes is made with an incomplete drill, charging of the openings and their blasting, dispatch of the rock, after blasting first of outline openings, for formation of the screening peephole, and then of breaking holes and mucking of the rock, similar operations are performed on the underlying subbench of the lower high bench, at the development of the lower high bench, the development of the upper and lower benches is conducted by doubling of the working subbenches, at the development of the lower subbench of the upper high bench the outline openings are drilled to the whole height of the doubled bench, the buffer openings are drilled at a distance of 12 to 13 diameters of the charge from the outline openings and to a depth at least corresponding to the height of one working subbench with a redrill equal to 6-8 diameters of the charge, the first and last rows of the breaking holes are drilled with a redrill, equal to 4-5 diameters of the charge, and the incomplete drill of the middle row of the breaking holes makes up 7-8 diameters of the charge, after blasting of the buffer and breaking opening and mucking of the rock a crest is formed, from whose surface on the side of the slope outline and buffer openings are drilled, the first ones - to the height of doubled subbenches, and the second ones - to the height at least of one lower working subbench, then the breaking openings to the same height as in the above - and underlying subbenches and for production of a natural protective bank on the upper section of the lower high bench in the section of the berm the formed ridge is liquidated by drilling, charging and blasting of the openings of small diameter and depth.
EFFECT: enhanced stability of high benches on the outline of the open pit.
2 cl, 3 dwg, 1 ex
Title | Year | Author | Number |
---|---|---|---|
PROCESS OF ARRANGEMENT OF HIGH WALLS IN OUTLINE OF STRIPPING | 2002 |
|
RU2224110C1 |
METHOD OF SLOPING HIGH BENCHES ON OPENCAST LIMITING CONTOUR | 2000 |
|
RU2178079C1 |
METHOD FOR PROTECTION OF SAFETY BENCH IN OPEN PIT | 1991 |
|
RU2023159C1 |
METHOD FOR SLOPING OF BENCHES | 1991 |
|
RU2068094C1 |
METHOD TO PROVIDE FOR STABILITY OF HIGH LEDGES | 2008 |
|
RU2392434C1 |
METHOD OF MINING BENCHES IN QUARRY | 0 |
|
SU1518651A1 |
METHOD FOR DEVELOPMENT OF ROCKS IN OPEN PIT RECONSTRUCTION | 2009 |
|
RU2395688C1 |
METHOD OF OPEN-PIT MINING | 1996 |
|
RU2098627C1 |
METHOD OF SLOT MAKING IN FORMATION OF BANK SLOPES IN OPENCASTS | 2001 |
|
RU2186983C1 |
0 |
|
SU1670133A1 |
Authors
Dates
2005-06-27—Published
2003-04-07—Filed