FIELD: construction.
SUBSTANCE: method includes consistently following technological operations: in the beginning the pilot hole is drilled to design depth by the hollow, tight boring reciprocating screw supplied in its bottom part with a bar chisel with a slip sliding valve and inbuilt ink-jet monitors, with adjustable rotation speed of a boring reciprocating screw to 60 rpm, clockwise, then, having increased rotation speed of a boring reciprocating screw to 120 rpm by means of inbuilt ink-jet monitors, design quantity of a water cement mix is delivered by directed jets under the set high pressure not less than 6 MPa, than scour a ground and create below widening of pilot hole from a soil-cement mix due to vertical, back and forth motion of a rotating boring reciprocating screw, thus, the amplitude of back and forth motions of a boring reciprocating screw corresponds to the set design height of created widening of a pilot hole, and the total amount of a delivered water-cement mix in a hole should not be more than it one-and-a-half-fold size, then a slip sliding valve in a bar chisel is opened and, with rotating of a boring reciprocating screw counter-clockwise with a speed no more than 60 rpm, lifting of a boring reciprocating screw on height equal to a double spacing of a reciprocating screw flange is carried out, and only after that, under a reduced pressure of 0.5 MPa through a slip sliding valve the fine-grained concrete is delivered and simultaneously the back and forth motions of a boring reciprocating screw is carried out, with amplitude equal to a widening height till the moment of the beginning of the fine-grained concrete outcropping from a hole mouth, then a boring reciprocating screw is taken out without rotation and simultaneously the fine-grained concrete is delivered under the pressure of 0.15 MPa, a prefabricated reinforcement cage is set in a hole, the fine-grained concrete is moulded in a hole by the pressure not less than 0.15 MPa, thus the fine-grained concrete volume should exceed the water cement mix volume delivered to a hole not less than on 10%.
EFFECT: new method of drill-injection stilts formation.
3 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR ERECTION OF BORED PILE WITH SOIL-CEMENT BROADENINGS IN WEAK SOILS ZONE AND DEVICE FOR ITS IMPLEMENTATION (VERSIONS) | 2019 |
|
RU2725363C1 |
DRILL STRING FOR ERECTION OF BORED PILE IN SOIL-CEMENT CLADDING | 2019 |
|
RU2735077C1 |
METHOD FOR STRENGTHENING SHALLOW FOUNDATIONS | 2017 |
|
RU2672699C1 |
METHOD OF AUGER PILE CONSTRUCTION | 2016 |
|
RU2634759C1 |
METHOD FOR CONSTRUCTING DRILLED PILE IN PERMAFROST SOIL | 2023 |
|
RU2803751C1 |
METHOD FOR ERECTION OF BORED PILE IN SOIL-CEMENT COATING | 2019 |
|
RU2720047C1 |
METHOD TO MAINTAIN INITIAL STRESSED-DEFORMED CONDITION OF SOIL IN ZONE OF EXISTING BUILDING FOUNDATION | 2010 |
|
RU2422592C1 |
DRILLING ASSEMBLY FOR GROUND COMPACTION IN WELL | 2004 |
|
RU2255183C1 |
METHOD OF REINFORCEMENT OF FOUNDATIONS | 2008 |
|
RU2360071C1 |
BORED PILE MANUFACTURING METHOD | 2019 |
|
RU2706848C1 |
Authors
Dates
2008-06-20—Published
2006-11-30—Filed