FIELD: oil and gas production.
SUBSTANCE: procedure consists in following stages: in lowering disconnecting column into borehole, also, drill column contains one or several couplings, one or several couplings wrapped with filter and multitude of swelling packers arranged around shank end at specified distance; and in swelling at least one of swelling packers to disconnect zones of one or several chosen intervals. Also, one or several couplings wrapped with filter and one or several couplings are arranged around the shank end at specified distance from each other for placement at least one or several couplings wrapped with filter and at least one or several couplings in one or several chosen intervals. Inside the shank end there is installed a shifter. The shifter controls positioning one or several couplings and one or several couplings wrapped with filter. The actuated shifter drives one or several couplings into an open position to intensify inflow from at least one or several chosen intervals, when fluid medium is supplied via one or several orifices of the shank end and to one or several orifices in one or several couplings. Additionally, the shifter is actuated to drive one or several couplings into a closed position to a repeated disconnection of zones of at least one or several chosen intervals. Further, the shifter is actuated to drive one or several couplings wrapped with filter in an open position to facilitate flow of produced fluid from at least one or several chosen intervals via at least one or several orifices in the shank end and via multitude orifices in at least one or several couplings wrapped with filter.
EFFECT: raised efficiency of procedure.
11 cl, 29 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF BOREHOLE CONDITIONING WITH COLLECTION OF PRODUCTIVE INTERVALS | 2007 |
|
RU2395667C1 |
METHOD OF ELIMINATING PROPPANT DEPOSITION CONDITIONS DURING WELL COMPLETION | 2015 |
|
RU2658400C1 |
METHOD OF ELIMINATING PROPPANT DEPOSITION CONDITIONS DURING WELL COMPLETION | 2015 |
|
RU2664989C1 |
METHOD FOR COMPLETION OF CONSTRUCTION OF PRODUCTION WELL WITH HORIZONTAL END OF WELLBORE | 2019 |
|
RU2726096C1 |
METHOD AND SYSTEM FOR HYDRAULIC FRACTURING | 2010 |
|
RU2671373C2 |
BYPASS ARRANGEMENT OF GRAVEL FILTER | 2013 |
|
RU2588508C2 |
LINER CEMENTING ASSEMBLY AND NOSE-TO-TOE INSTALLATION OF GRAVEL FILTER PER ONE RUN | 2013 |
|
RU2578064C2 |
COMPLETION ASSEMBLY AND METHOD FOR WELL COMPLETION IN UNDERGROUND FORMATION | 2008 |
|
RU2431036C2 |
DOWNHOLE TESTING METHOD IN OPEN HOLE | 2016 |
|
RU2625126C1 |
METHODS AND ASSEMBLY FOR ISOLATION OF ZONES IN WELL BOREHOLE | 2012 |
|
RU2535320C2 |
Authors
Dates
2011-02-20—Published
2008-04-02—Filed