FIELD: machine building.
SUBSTANCE: when pipeline is lifted for cleaning from old insulation and for application of new insulation, height of lifting, selection of quantity and arrangement of pipe layers are determined considering limited deformation of pipeline metal in places with minimal value of radius of curvature causing change of critical temperature of metal brittleness to values of temperature of environment.
EFFECT: prevented destruction of pipeline at insulation-laying operations due to transition of deformed pipeline into brittle condition at reduced temperature of environment; raised safety of repair operations.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR REPAIRING DEFECTIVE PIPELINE SECTION OF ABOVEGROUND GASKET | 2015 |
|
RU2616735C1 |
0 |
|
SU278319A1 | |
METHOD OF REPAIR OF INSULATING COATINGS | 2001 |
|
RU2197668C2 |
METHOD FOR HOLDING PIPELINE DURING ITS MECHANIZED CLEANING OF INSULATION AT THE EDGE OF TRENCH | 2022 |
|
RU2803684C1 |
METHOD OF REPAIR OF PIPELINE WITH INSULATION COATING | 2008 |
|
RU2460930C2 |
PROCEDURE FOR PIPELAY | 2010 |
|
RU2436007C1 |
METHOD OF REPAIRING LENGTHY PIPE-LINE | 0 |
|
SU1451423A1 |
METHOD OF REJECTION OF PIPES WITH CORRUGATIONS (DENTS) AT MAJOR REPAIR OF PIPE LINES | 2000 |
|
RU2179683C1 |
METHOD OF PIPELINE REPAIR | 2011 |
|
RU2493468C2 |
METHOD FOR REPAIR OF EXTENDED PIPELINE WITH LOCAL FLAWS | 1994 |
|
RU2094691C1 |
Authors
Dates
2011-07-27—Published
2008-12-09—Filed