FIELD: mining.
SUBSTANCE: during reinforcement of mine workings with anchor support in rocks prone to soil heaping there drilled are bore pits into the roof and sides of mine working; and anchor bars, support elements and tie bars are installed in them. Anchors are installed into the sides at an angle to bedding. The first anchor is located at minimum technically possible distance from the roof of mine working. Length of side anchors is determined by mathematical formula.
EFFECT: reducing the soil heaping of mine workings.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR SUPPORTING SOIL OF MINE WORKINGS | 2011 |
|
RU2459907C1 |
METHOD OF GUARDING OF WORKINGS IN HEAVING SOILS | 1990 |
|
RU2007577C1 |
METHOD FOR REINFORCEMENT OF MINES SOIL | 2011 |
|
RU2468207C1 |
REINFORCEMENT METHOD OF MINE WORKINGS WITH ANCHOR SUPPORT | 2010 |
|
RU2435959C1 |
METHOD FOR FORTIFYING MINE WORKINGS DRIVEN IN ROCK MATTER LIABLE TO HEAVING | 1995 |
|
RU2134350C1 |
METHOD FOR MINE LINING | 2004 |
|
RU2308599C2 |
METHOD OF SECURING DEVELOPMENT WORKINGS | 0 |
|
SU1751347A1 |
MINE WORKING SOIL ANTI-SWELLING METHOD | 2010 |
|
RU2438018C1 |
METHOD OF MINE WORKINGS SUPPORT | 2000 |
|
RU2177550C1 |
METHOD FOR CONDUCTING MINING WORKS IN DEVELOPMENT OF FLAT COAL BEDS | 2022 |
|
RU2805691C1 |
Authors
Dates
2012-03-10—Published
2010-08-09—Filed