FIELD: construction.
SUBSTANCE: method consists in installation of modules in an ice cover by means of their placement prior to river freezing, with subsequent freezing-in of modules into ice as the river freezes. Besides, the module dome is installed above the water surface, and the lower end of the module is below the level of the expected ice cover. The module is filled with air via an air duct attached to a tight dome of a module, at the open mechanical valve, afterwards the valve is closed. At the same time, whenever a lane is produced under influence of climatic factors, by opening the mechanical valve, air is released from the module with filling of its cavity with water from lower layers. The method is realised by means of a module comprising a vessel installed on bottom supports with arrangement of its ends outside the borders of the ice monolith, and a tight dome. An air duct with a mechanical valve is connected to a dome. The module is arranged in the form of a nozzle with a downward expansion.
EFFECT: efficient weakening of river ice cover monolith and development of conditions for free discharge and passage of thawed waters.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR WEAKENING OF ICE COVER ON THE RIVER AND A DEVICE FOR ITS IMPLEMENTATION | 2012 |
|
RU2577589C2 |
METHOD TO CREATE REINFORCED ICE BRIDGE FOR WIDE PONDS | 2013 |
|
RU2569694C2 |
METHOD FOR REGULATION OF WATER LEVEL IN RIVER | 1998 |
|
RU2137879C1 |
DEVICE FOR ROPE FEED TO HIGH-RISE DANGER AREA | 2010 |
|
RU2428230C1 |
METHOD OF OIL GATHERING FROM UNDER ICE COVER IN FLOW BASIN | 2002 |
|
RU2224842C1 |
STORAGE TANK FOR LIQUEFIED GASES AND EXPLOSIVE LIQUIDS | 1990 |
|
RU2008550C1 |
SPACECRAFT | 2004 |
|
RU2271965C2 |
METHOD OF ICE COVER DESTRUCTION AND DEVICE FOR ICE COVER DESTRUCTION | 2014 |
|
RU2552753C1 |
STORAGE TANK FOR LIQUEFIED GASES AND EXPLOSIVE LIQUIDS | 1990 |
|
RU2008551C1 |
METHOD OF CONSTRUCTING AN ICE HYDRAULIC STRUCTURE | 0 |
|
SU1129284A1 |
Authors
Dates
2012-06-10—Published
2010-05-18—Filed