FIELD: construction.
SUBSTANCE: method to erect a railway track consists in the fact that a monolithic concrete base is formed with evenness making ± (0.25 mm - 1.99 mm) per one running metre of any section of the monolithic base, viewed in plan, in its transverse profile and its longitudinal profile. After a concrete mix has hardened, multiple intermediate rail braces are installed on the formed monolithic base, and with their help rails are fixed on the monolithic base. The intermediate rail brace comprises a rail pad with a section bent down relative to the upper surface of the pad by an angle of around 90 degrees. The design of the rail track includes many intermediate rail braces fixed on the concrete base, comprising on its surface at least one longitudinal groove with vertical walls, which a bent section of the intermediate brace rail paid adjoins to form a pair of engagement: a bent section of a rail pad - a vertical wall of a groove. The design of the rail track also includes rails rigidly fixed to the base by means of multiple intermediate rail braces.
EFFECT: possibility to provide for erection of a more universal railway track within a shorter period of time, which is suitable for high loads and for any sections of a track.
19 cl, 5 dwg
Title | Year | Author | Number |
---|---|---|---|
RAIL FASTENING | 2014 |
|
RU2557098C1 |
METHOD OF AND DEVICE FOR REDUCING LEVEL OF VIBRATIONS OF RAIL TRACK BASE | 2002 |
|
RU2207420C1 |
RAIL TRACK | 2002 |
|
RU2224834C1 |
TRACK UPPER STRUCTURE DESIGN | 2007 |
|
RU2352706C1 |
DEVICE TO REDUCE RAILWAY TRACK VIBRATION LEVEL | 2002 |
|
RU2221911C2 |
RAILWAY TRACK SUPERSTRUCTURE IN TUNNEL | 2020 |
|
RU2733595C1 |
INTERMEDIATE RAIL FASTENING | 2023 |
|
RU2805596C1 |
METHOD FOR INSTALLATION OF PERMANENT WAY | 2007 |
|
RU2352705C1 |
RAIL FASTENING | 1996 |
|
RU2097468C1 |
TRACK OVERSTRUCTURE | 0 |
|
SU1019041A1 |
Authors
Dates
2012-06-27—Published
2011-04-11—Filed