FIELD: oil and gas industry.
SUBSTANCE: sand bridge is installed in a gross interval of carrier bed. A flushing fluid is injected into a sealed well with fixation of injection pressure and volume of the injected flushing fluid, with simultaneous building of a dependence curve. According to the schedule the pressure of "leakage" start is decided in the deviation point. The excess pressure is relieved with fixation of the volume of the released well flushing fluid, and the well head is unsealed. A cement bridge is installed by means of pushing of a cement mortar in the volume determined from the inequation, with volume flow rate calculated in accordance with the formula and simultaneous lifting of a hydraulic monitor from the carrier bed roof with entry into an operating string, with the speed calculated in accordance with the dependence. A sleeve of cement mortar is left in the string in the volume required to fill the vault part of the damage cavern. The flushing fluid is injected into the well in the volume that does not exceed the volume of the cement mortar sleeve or before achievement of the "leakage" start pressure. Hardening of the cement mortar is expected with pressure maintenance, afterwards the cement and the sand bridges are drilled.
EFFECT: increased quality of roof propping in a bottomhole formation zone in wells with open design of a bottomhole, when a vault part of a damage cavern spreads below a bottom of an operating string.
1 cl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF INSTALLATION OF CEMENT BRIDGE | 1999 |
|
RU2170334C2 |
METHOD OF INSTALLATION OF CEMENT BRIDGING PLUG | 1999 |
|
RU2168609C2 |
METHOD OF RECOVERY OF BOTTOM-HOLE FORMATION ZONE OF GAS WELL | 2000 |
|
RU2183724C2 |
METHOD OF WELLBORE CLEANING | 1999 |
|
RU2168000C2 |
METHOD OF WELLBORE CLEANING | 1999 |
|
RU2168603C2 |
METHOD OF INJECTING INTO WELLS | 1994 |
|
RU2109128C1 |
METHOD OF ACID LONGITUDINAL HYDRAULIC FRACTURING OF LOW-PERMEABLE TERRIGENOUS COLLECTOR | 2014 |
|
RU2543004C1 |
UNIVERSAL DEVICE FOR DRILLING, CLEANING OF CAVERN AND INSTALLING OF CEMENT PLUG | 2012 |
|
RU2513788C1 |
METHOD TO FIX PROCESS WELLS OF UNDERGROUND STORAGES OF GASEOUS AND LIQUID HYDROCARBONS (VERSIONS) | 2015 |
|
RU2576416C1 |
WATER AND GAS INFLUX LIMITING METHOD WITH WELL PRODUCTIVITY RECOVERY | 2013 |
|
RU2539047C1 |
Authors
Dates
2013-04-27—Published
2011-11-08—Filed