FIELD: mining.
SUBSTANCE: for realisation of the method, drainage-degassing wells are drilled in zones of higher cracking outside the limits of the prepared mine. Wells are drilled in the bottom-up direction in the close proximity to the profile of the prepared mine. Pumping of gas saturated drainage brines is carried out until the level of the depression curve is set below the horizon of breaking works, and it is maintained at this level for the entire period of mining. Besides, in process of wells drilling the minimum permissible distance to the profile of the prepared mine is accepted as 0.035 m per each running metre of the well.
EFFECT: method makes it possible to increase safety of underground mining works due to reduce amount of arriving fuel gas and natural waters to mines from deep and deposit-adjacent horizons of earth interior.
2 cl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR RECONSTRUCTION OF A FLOODED MINE MINED BY OPEN-UNDERGROUND METHOD | 2023 |
|
RU2798370C1 |
METHOD FOR DEGASSING OF OVERWORKED ADJACENT SEAMS | 2020 |
|
RU2749707C1 |
METHOD OF DEGASSSING OF OVERWORKED ACCOMPANYING BED | 2017 |
|
RU2666570C1 |
METHOD FOR DEVELOPING KIMBERLITE DEPOSITS | 2017 |
|
RU2664281C1 |
METHOD TO DEGAS COAL-BEARING SERIES | 2012 |
|
RU2487246C1 |
METHOD OF HYDROGEODYNAMIC CLEANING OF WATER BEDS FROM PETROLEUM PRODUCTS AND HYDROGEODYNAMIC TRAP FOR PETROLEUM PRODUCTS | 2017 |
|
RU2666561C1 |
COAL-BEARING STRATA DEGASATION METHOD | 2008 |
|
RU2382882C1 |
METHOD FOR OPENCAST MINING OF FLOODED MINERAL DEPOSITS | 1994 |
|
RU2114307C1 |
METHOD OF CREATING WATER-RESISTANT FILLING MASS | 2016 |
|
RU2642750C1 |
PROCEDURE FOR DEGASSING GAS BEARING ORE AND COAL DEPOSITS AT DEVELOPMENT OF MINERALS | 2009 |
|
RU2394159C1 |
Authors
Dates
2013-07-20—Published
2011-12-21—Filed