METHOD OF OPEN AND UNDERGROUND MINING OF SERIES OF SEMI-STEEP COAL LAYERS Russian patent published in 2015 - IPC E21C41/00 E21C41/18 

Abstract RU 2563895 C1

FIELD: mining.

SUBSTANCE: method of open and underground mining of series of steeply dipping coal layers includes the separation of the mining lease into sections, on the day surface of each section the working platform is arranged by removal of deposits above internal layer of non-working thickness. At the output of this layer the mouth of inclined mining is arranged which is performed towards one of boundaries of the mining lease along spreading of layers. Inclined drift is performed rectilinearly along the layer of non-working thickness with an out-of-seam dilution of rocks of the roof and the soil to the level of the underlying horizontal layer where the horizontal layered chamber is formed. From the layered chamber the cross-cut is performed at first towards overlying layers, then - backwards, thus opening all layers of the series of working power. Coal in the layer is extracted by mobile mechanization devices in the horizontal extraction chamber up to one of boundaries of the mining lease along spreading consistently in all layers of the series of working thickness. Then the inclined drift is deepened down to the level of the following underlying layer with keeping of proportional ledge between layers. Delivery of the broken-down coal along the inclined drift is performed by a tape conveyor. The mouth of each subsequent inclined drift is arranged at the following working site at the distance from previous one, approximately equal to total length in plan of projections of inclined drift and the excavated extraction chamber. At the final stage when arranging the last inclined drift the coal is extracted in underlying layers as it is described above, and in the overlying ones - towards opposite boundary of the mining lease along spreading as well. On the excavated working sites the disturbed landscape is reinstated.

EFFECT: design improvement the invention allows to improve efficiency of arrangement of the series of layers.

3 dwg

Similar patents RU2563895C1

Title Year Author Number
METHOD OF OPEN-UNDERGROUND DEVELOPMENT OF THICK SINGLE STEEPLY INCLINED COAL SEAM 2014
  • Anferov Boris Alekseevich
  • Kuznetsova Ljudmila Vasil'Evna
RU2555997C1
METHOD OPEN UNDERGROUND MINING OF STEEP COAL BEDS 2012
  • Anferov Boris Alekseevich
  • Kuznetsova Ljudmila Vasil'Evna
RU2499129C1
METHOD FOR OPEN-UNDERGROUND MINING OF THICK STEEP COAL BED 2012
  • Anferov Boris Alekseevich
  • Kuznetsova Ljudmila Vasil'Evna
RU2490454C1
METHOD OF OPEN-UNDERGROUND DEVELOPMENT OF COAL BED, LYING IN THE FORM OF BRACHYSYNCLINE 2017
  • Anferov Boris Alekseevich
  • Kuznetsova Lyudmila Vasilevna
RU2651833C1
COMBINED METHOD FOR MINING OF COAL SEAMSERIES 1992
  • Petrov A.I.
  • Jakovlev N.I.
  • Poturilov A.M.
  • Sukhovol'Skij S.N.
  • Kozlikin A.A.
RU2039257C1
METHOD FOR DEVELOPMENT OF STRATA DEPOSITS OF MINERALS 1996
  • Chervjakov E.V.
  • Pugachev E.V.
  • Frjanov V.N.
  • Ljubogoshchev V.I.
RU2102592C1
METHOD OF CONTROL OF AEROGASDYNAMIC PROCESSES IN MINING OF FORMATION OF COAL SEAMS 1995
RU2101499C1
COMBINED METHOD OF MINING OF FORMATION OF STEEPLY DIPPING COAL SEAMS 1996
  • Krugljak A.S.
  • Chernodarov A.I.
  • Shakhurdin S.A.
  • Jakovlev N.I.
  • Sukhovol'Skij S.N.
  • Trojan N.P.
  • Sitnikov G.A.
  • Zhukov E.L.
  • Aksenov G.I.
RU2099524C1
METHOD OF COMBINED MINING OF BED MINERAL DEPOSITS 0
  • Popkov Mikhail Petrovich
  • Nifontov Albert Ivanovich
  • Yalevskij Vladlen Danilovich
  • Fedorin Valerij Aleksandrovich
  • Nikishichev Boris Grigorevich
  • Mikheev Oleg Vitalevich
SU1751333A1
METHOD FOR THICK STEEPLY INCLINED FIRE-HAZARDOUS BED MINING WITH CAVING 2004
  • Sitnikov G.A.
  • Smetjuk V.S.
  • Bojko S.V.
  • Sukhovol'Skij S.N.
RU2263213C1

RU 2 563 895 C1

Authors

Anferov Boris Alekseevich

Kuznetsova Ljudmila Vasil'Evna

Dates

2015-09-27Published

2014-10-06Filed