FIELD: construction.
SUBSTANCE: method of sinking of the pile includes driving of the pile into soil to a required depth by a gravitational hammer through a guiding conductor with subsequent fixing by embedment in a grillage. The pile is a metal pipe of a large diameter from 1000 to 2000 mm with a cone-shaped pointed closed end fitted with a rock cutting tip, and an anvil, and the anvil is designed in the form of a ferroconcrete cone-shaped closed end of the pile and its lower part with the ratio of the height of the filled lower part of the pile shaft to the height of the closed end cone of 0.5-1.0, reinforcing of the tip is performed in the form of curved reinforcing rods, and from above of the ferroconcrete anvil a metal circular board is installed. The pile shaft of a large diameter from 1000 to 2000 mm in the lower part is fitted with blades which are evenly placed along the diameter. The blades are rigidly fixed on the pile shaft and are made inclined at the angle of 5-30° to the pile axis, the ratio of the length of each blade to the length of the diameter of the shaft pile is selected within 0.5…1.0, the ratio of the width of each blade to the length of the diameter of the pile shaft is selected within 0.15…0.30. Bottom edges of the blades are installed at a distance from the cone of the closed end, equal to 0.5-1.0 diameters of the pile shaft, and the number n of blades placed along the diameter of the pile shaft depending on the diameter is determined from the given ratio.
EFFECT: increase of the bearing ability of the pile, decrease of material consumption and labour input.
3 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
UNIVERSAL DISMOUNTABLE ICE CUTTER | 2020 |
|
RU2746339C1 |
METHOD TO IMMERSE PILES IN SEASONAL-FROZEN GROUND | 2019 |
|
RU2707228C1 |
CONSTRUCTION METHOD OF PILE SCREW-BLADE FOUNDATION OF STRUCTURE, AND ITS ARRANGEMENT | 2013 |
|
RU2537463C1 |
MANUFACTURING METHOD OF ASSEMBLY ATTACHING PILE TO AVAILABLE FOUNDATION AT ITS BEING REINFORCED (VERSIONS) | 2008 |
|
RU2385384C1 |
ANTENNA SUPPORT OF TOWER TYPE | 2015 |
|
RU2588269C1 |
METHOD FOR CONSTRUCTING BRIDGE SUPPORT IN WATER AREA | 2023 |
|
RU2809049C1 |
MULTI-PILE FOUNDATION AND METHOD FOR ERECTION THEREOF ON FROZEN SOILS | 2015 |
|
RU2584019C1 |
PRECAST PILE WITH WIDENING | 2016 |
|
RU2646267C1 |
TELESCOPIC SCREW PILE WITH LEADER PILE | 2021 |
|
RU2763573C1 |
EXTENDABLE SCREW PILE AND METHOD FOR ITS ARRANGEMENT | 2021 |
|
RU2769003C1 |
Authors
Dates
2016-03-10—Published
2014-08-12—Filed