FIELD: construction.
SUBSTANCE: method of the bridge structure reconstruction includes the installation of temporary supports on temporary piles, the installation of thrust and supporting crossarms. The temporary supports are installed in pairs from different sides of the bridge structure, after which a thrust crossarm is mounted on each pair of the temporary supports across the bridge structure. Thereinafter, the through openings are drilled in a beam of the bridge structure, and then the bundles of ropes are stretched, first through the thrust crossarm, then into the through openings of the beam of the bridge structure, then through the supporting crossarm previously arranged on the ground under the beam of the bridge structure. Jacks are installed on the thrust crossarm at the points of the rope bundles output, and the supporting crossarm is pulled up with the beam resting on it. Then the existing ropes stretched in the upper slab along the entire bridge structure are strained. Then the inner surface of the lower slab of the beam is reinforced by laying rope bundles into pre-made longitudinal channels along the entire bridge structure, and then these rope bundles are strained and fixed. The thrust and supporting crossarms and the supports with the piles are dismantled.
EFFECT: reinforcing the existing span structure of the bridge.
3 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR RECONSTRUCTION OF REINFORCED CONCRETE BOX-SHAPED SUPERSTRUCTURE IN THE OVERHEAD SECTION OF A BRIDGE | 2022 |
|
RU2801014C1 |
METHOD FOR LIFTING OF REINFORCED CONCRETE BEAM OF BRIDGEWORK DURING REPAIR OF SUPPORT CROSSBAR OR REPLACEMENT OF SUPPORT PARTS | 2012 |
|
RU2495183C1 |
METHOD AND DEVICE FOR BRIDGE PIER RECONSTRUCTION DURING PIER GIRDER REPAIR OR SUPPORT PARTS REPLACEMENT | 2005 |
|
RU2309217C2 |
METHOD OF DISMANTLING OF DAMAGED BEAM OF BRIDGE SPAN | 2014 |
|
RU2549664C1 |
METHOD FOR TRANSVERSE RELOCATION OF BRIDGE SUPERSTRUCTURE FOR EXTENDED COLLAR BEAM | 2014 |
|
RU2557020C1 |
METHOD FOR TRANSFER OF LONG-SPAN STEAM-AND-WATER MIXTURE DELIVERY PIPELINE OVER CANYON LOCATED IN SEISMICALLY ACTIVE ZONE | 2023 |
|
RU2815705C1 |
ANCHORAGE FOR SECURING BRIDGE FRAMEWORK TO BRIDGE FOOTING | 2002 |
|
RU2209869C1 |
BRIDGE RECONSTRUCTION METHOD USING TRANSVERSE RELOCATION OF EXISTING REINFORCED-CONCRETE SOLID SUPERSTRUCTURE | 2014 |
|
RU2556766C1 |
CONSTRUCTION METHOD AND DESIGN OF OVERPASSES AND BRIDGES UNDER CONDITIONS OF PERMAFROST | 2012 |
|
RU2513574C2 |
METHOD TO EXPAND BRIDGE STRUCTURE USING CABLE SYSTEM | 2013 |
|
RU2539461C1 |
Authors
Dates
2017-04-26—Published
2016-02-26—Filed