Abstract RU 2755778 C1

FIELD: oil industry.

SUBSTANCE: invention relates to the oil industry. In the method for preventing the formation of ARPD in lift pipes during gas-lift operation of oil wells, initial data are obtained on the component compositions of the formation fluid and associated petroleum gas APG, which is used as a working agent, then it is purified from hydrogen sulfide and carbon dioxide, then the purified associated gas is injected oil gas without changing its hydrocarbon composition and determine the temperature T1 of oil saturation with paraffin and the depth of its formation in the well, taking into account the change in the composition of oil when injecting associated petroleum gas. The ratio of light and heavy fractions of the injected associated petroleum gas is changed and the temperature T2 of oil saturation with paraffin and the depth of its formation for a given ratio of light and heavy fractions are determined. If T2 > T1, the ratio of light and heavy fractions of the injected working agent is changed again and the determination of the temperature T2 of oil saturation with paraffin and the depth of its formation is repeated. If T2 < T1, the resulting temperature is taken as a new initial version. The condition of the possibility of ensuring the required ratio of fractions based on the component composition of APG is checked, if it is confirmed, then this procedure is repeated for another variant of the ratio of light and heavy fractions, if not confirmed, the optimal variant of the required amount of flow rate of the working agent is selected at the lowest temperature of oil saturation with paraffin. Hot APG is injected into the annulus of the well between the tubing string and the production string, while the optimal flow rate of hot APG is preliminarily determined based on the volume of the injected working agent and the smallest value of its injection depth. The interval for running the process string with a heat-insulating coating with an optimal thickness of 20-35 mm is set below the depth of hot APG injection into the well by no more than 30 m. The heat-insulating coating of the technological column is made of polyurethane. The injected APG is preheated to 90-105°C, the mode of hot APG injection into the well is determined by predicting the rate of formation of organic deposits in the tubing string to reduce the well flow rate and increase the thickness of the deposits over time - the area of the intersection of the dependences of the change in the flow rate of the well and the thickness of the deposits corresponds to the optimal value of the intertreatment period of the well operation, then hot APG is continuously injected into the gas-lift well until the planned value of the current flow rate of the well is restored, after which the constant pressure valve is closed.

EFFECT: increasing the efficiency of gas-lift wells, complicated by the intensive formation of asphalt-resin-paraffin deposits of ARPD in lift pipes during the production of highly paraffinic oil, increasing the overhaul period of the well.

1 cl, 10 dwg, 2 tbl, 4 ex

Similar patents RU2755778C1

Title Year Author Number
METHOD OF PREVENTING FORMATION OF ASPHALTENE, RESINOUS PARAFFIN DEPOSITS (ARPD) IN LIFT PIPES DURING GAS-LIFT OPERATION OF OIL WELLS 2020
  • Nguen Van Tkhang
  • Rogachev Mikhail Konstantinovich
  • Aleksandrov Aleksandr Nikolaevich
  • Khasanov Aleksandr Andreevich
RU2740462C1
METHOD OF CONTROLLING FORMATION OF ASPHALTENE SEDIMENTS DURING PRODUCTION OF HIGH POUR POINT ANOMALOUS OIL 2021
  • Aleksandrov Aleksandr Nikolaevich
  • Rogachev Mikhail Konstantinovich
  • Nguen Van Tkhang
  • Akshaev Vladislav Ivanovich
RU2766996C1
METHOD FOR PREVENTING FORMATION OF ASPHALT, RESIN AND PARAFFIN DEPOSITS 2023
  • Valiev Dinar Zinnurovich
  • Kemalov Alim Feizrakhmanovich
  • Kemalov Ruslan Alimovich
  • Bryzgalov Nikolai Innokentevich
  • Alfaiaad Assim Gani Khashim
RU2808077C1
METHOD FOR ASPHALT-TAR-PARAFFIN DEPOSITS PREVENTION IN OIL PRODUCTION EQUIPMENT 2005
  • Petrov Nikolaj Aleksandrovich
  • Zolotoevskij Vladimir Semenovich
  • Vetland Mikhail Leonidovich
  • Beljaev Vitalij Stepanovich
RU2298642C1
WELL DEWAXING METHOD 2014
  • Ibragimov Nail' Gabdulbarievich
  • Taziev Mirgazijan Zakievich
  • Rakhmanov Ajrat Rafkatovich
  • Dzhafarov Marzakhan Atakishi Ogly
  • Absaljamov Ruslan Shamilevich
RU2553129C1
METHOD FOR REMOVING OF DEPOSITS FROM FLOW COLUMN OF OIL WELLS 2016
  • Denislamov Ildar Zafirovich
  • Gniloukhov Daniil Sergeevich
  • Khabibullin Radik Ramzilovich
RU2610946C1
METHOD FOR BOREHOLE PRODUCTION OF HIGH-VISCOSITY OIL 2020
  • Denislamov Ildar Zafirovich
  • Ishbaev Rustam Rauilevich
  • Ishbaev Ramil Rauilevich
  • Abyzbaev Nikita Ibragimovich
RU2752304C1
METHOD FOR WELL CLEANING OF ASPHALT-TAR-PARAFFIN AND SULFIDE DEPOSITS 2004
  • Sadykov L.Ju.
  • Gabdullin R.F.
  • Garifullin F.S.
  • Khajbrakhmanov N.Kh.
  • Saitov I.R.
  • Garifullin I.Sh.
  • Gil'Mutdinov R.S.
  • Islamov M.K.
RU2266392C2
METHOD FOR THERMO-CHEMICAL WELL BORE ZONE CLEANING 2003
  • Motovilov Valentin Jur'Evich
RU2268998C2
METHOD OF REMOVING DEPOSITS FROM WELL EQUIPPED WITH ELECTRIC CENTRIFUGAL PUMP 2016
  • Ibragimov Nail Gabdulbarievich
  • Rakhmanov Ajrat Rafkatovich
  • Malkovskij Maksim Aleksandrovich
  • Abakumov Anton Vladimirovich
  • Latfullin Rustem Ruslanovich
RU2603982C1

RU 2 755 778 C1

Authors

Nguen Van Tkhang

Rogachev Mikhail Konstantinovich

Aleksandrov Aleksandr Nikolaevich

Dates

2021-09-21Published

2021-02-20Filed