FIELD: oil industry.
SUBSTANCE: invention relates to the oil industry, in particular to a method for conducting water isolation work in a well during the development of an oil deposit underlain by water. The method for isolating water in the bottom-hole zone of a production well with hydraulic fracturing involves pouring an insulating composition into the well with a preliminary determination of the volume of the insulating composition and pressing it into the formation. At the same time, a well is selected that is water-encroached exclusively due to the formation of a cone of water. The required volume of the insulating composition Vgen. is determined by the formula V gen. = V1 + Vgen.fr., where V1 is the volume of the well from the lower edge of the perforation to the bottom of the well, Vgen.fr. is the volume of the aquifer of the fractured space. Volume Vgen.fr. it is calculated by the formula Vgen.fr. = Vpr.∙h3/h1, where Vpr. is the volume of proppant injected during hydraulic fracturing, m3, h1 is the capacity of the oil reservoir, m, h3 is the capacity of the aquifer part of the reservoir, m. The insulating composition of the volume of Vgen. is poured. into the selected well, a pressing fluid is pumped into the well to press an insulating composition through the perforation holes of the well, creating excessive hydrostatic pressure of the sales fluid column, for gravitational replacement of reservoir water in the fracture and the formation of a waterproof anti-filtration insulating shield at the base of the fracture in the bottom-hole zone of the formation. A weighted polymer solution is used as an insulating compound, and water is used as a pressing fluid. Moreover, an insulating composition and a pressing liquid of such density are chosen, at which the hydrostatic pressure of the column of the insulating composition and the hydrostatic pressure of the column of the pressing liquid exceeds the residual reservoir pressure.
EFFECT: increase in the efficiency of water isolation in the bottom-hole zone of oil-production wells with a simultaneous reduction in the complexity and duration of water isolation work.
1 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF RESTORATION OF WATER-FLOODED GAS OR GAS CONDENSATE WELL AFTER HYDRAULIC FRACTURING OF FORMATION | 2019 |
|
RU2740986C1 |
METHOD FOR LIMITING WATER INFLUX IN PRODUCTION WELL | 2011 |
|
RU2477789C1 |
WET GAS OR GAS CONDENSATE WELL RECOVERY METHOD AND ITS DROWNING PREVENTION DURING ITS FURTHER OPERATION | 2013 |
|
RU2534291C1 |
PROCEDURE FOR TREATMENT OF BOTTOMHOLE ZONE OF WELL | 2010 |
|
RU2422619C1 |
METHOD FOR DEVELOPMENT OF A DOMANIC OIL RESERVOIR | 2019 |
|
RU2733869C1 |
METHOD OF DEVELOPMENT OF OIL POOL IN CARBONATE RESERVOIRS OF FRACTURED-POROUS TYPE | 2000 |
|
RU2204703C2 |
METHOD FOR PROCESSING FACE-ADJACENT ZONE OF WELL | 2004 |
|
RU2260689C1 |
METHOD OF INCREASING OIL YIELD IN INHOMOGENEOUS, HIGHLY-FLOODED, POROUS AND FRACTURED-POROUS, LOW- AND HIGH-TEMPERATURE PRODUCTIVE STRATUM | 2013 |
|
RU2528805C1 |
METHOD FOR CARRYING OUT WATER SHUTOFF TREATMENT IN WELL | 2016 |
|
RU2622965C1 |
PROCEDURE FOR WATER SHUTOFF TREATMENT IN WELL | 2016 |
|
RU2618538C1 |
Authors
Dates
2022-05-16—Published
2021-06-28—Filed