FIELD: underground construction. SUBSTANCE: method includes driving the audits on boundaries of station tunnel with traffic tunnels, erection along axes of audits of supports in the form of column with supporting pivots and girders lain on columns, anchoring of columns with the help of reusable braces in side walls of audit, removal of braces, cyclic driving of station and traffic tunnels, and ground extraction by stopes equalling support spacing, erection of free parts of tunnel with their resting on supports, mounting the platform part of station tunnel in the form of concrete cast-in-situ plate and trough parts of lining of traffic tunnels and injection of cement mortar behind the exterior surface of tunnel lining. Distinguishing feature of the method i is in that the cast-in-situ plate is joined directly with trough parts of traffic tunnel and performed in course of driving of audits and tunnels are mounting and removal of audit temporary supports. In this case, removal of braces is effected in course of ground extraction in tunnels before their lining. EFFECT: higher efficiency. 3 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF CONSTRUCTION OF DEEP-SEATED SUBWAY STATION | 1993 |
|
RU2082884C1 |
METHOD OF CONSTRUCTION OF DEEP-SEATED SUBWAY STATION | 1993 |
|
RU2082883C1 |
METHOD FOR CONSTRUCTING UNDERGROUND STATION USING CLOSED METHOD OF CARRYING OUT WORK ON EXISTING UNDERGROUND LINE WITHOUT INTERRUPTING TRAIN TRAFFIC | 2023 |
|
RU2810984C1 |
METHOD OF CONSTRUCTING DEEP UNDERGROUND STATION ON OPERATING UNDERGROUND LINE WITHOUT INTERRUPTING TRAIN TRAFFIC | 2023 |
|
RU2825811C1 |
METHOD FOR CONSTRUCTING METRO STATION FROM PREFABRICATED ELEMENTS USING CLOSED METHOD OF PERFORMING WORK ON EXISTING METRO LINE WITHOUT INTERRUPTING TRAIN TRAFFIC | 2023 |
|
RU2815900C1 |
METHOD FOR ERECTING DEEP SUBWAY STATION | 1993 |
|
RU2061148C1 |
THREE-ARCH UNDERGROUND STATION OF THE CLOSED COLUMN-TYPE | 2022 |
|
RU2802893C1 |
METHOD OF ERECTING DEEP UNDERGROUNG STATION | 0 |
|
SU1763584A1 |
METHOD OF CONSTRUCTING SUBWAY PYLON STATION USING CLOSED METHOD OF PERFORMING WORKS ON OPERATING SUBWAY LINE WITHOUT INTERRUPTING TRAIN TRAFFIC | 2023 |
|
RU2824544C1 |
DOUBLE-LEVEL SINGLE-VAULT TRANSFER STATION UNIT OF DEEP SUBWAY | 1996 |
|
RU2131960C1 |
Authors
Dates
1998-01-20—Published
1997-04-23—Filed