FIELD: ice technology; erecting ice temporary bridge for freight hauling. SUBSTANCE: metal tubes are laid at angle to horizon on reservoir bottom at entry and exit points so that after ice cover has frozen their lower part occurs below ice and their upper part is above ice. Lower end of tubes is welded in advance. Cold air flowing inside tubes causes their icing and freezing of ice cover with reservoir bottom. EFFECT: enhanced strength of entry and exit of temporary bridge. 1 cl, 1 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR ERECTING TEMPORARY ICE BRIDGE | 2000 |
|
RU2171331C1 |
ICE CROSSING CONSTRUCTION PROCESS | 2000 |
|
RU2164975C1 |
METHOD FOR ERECTING TEMPORARY ICE BRIDGE | 2000 |
|
RU2171333C1 |
METHOD FOR ERECTING TEMPORARY ICE BRIDGE | 2000 |
|
RU2171332C1 |
METHOD TO INCREASE BEARING CAPACITY OF ICE COVER | 2018 |
|
RU2695190C1 |
METHOD FOR ERECTING ICE TEMPORARY BRIDGE | 1999 |
|
RU2170790C2 |
METHOD FOR MANUFACTURING LOAD-CARRYING ICE PLATFORM | 2000 |
|
RU2171335C1 |
METHOD OF BUILDING ICE CROSSING | 1998 |
|
RU2135685C1 |
METHOD TO INCREASE BEARING CAPACITY OF ICE COVER | 2018 |
|
RU2695577C1 |
METHOD FOR ERECTING TEMPORARY ICE BRIDGE | 2000 |
|
RU2171334C1 |
Authors
Dates
2001-07-20—Published
2000-02-04—Filed