FIELD: mining industry.
SUBSTANCE: method includes extraction of quarry to planned depth in stages with construction f boards with parameters, allowed from stability condition, shutting boards, finishing mineral resource massif. Building and shutting of temporary boards during extraction of steep layers of next level after change of order of extraction of opening and ore zones is started after construction and spacing in center of cut of well-like mine with vertical shelves, with parameters, which are provided for by minimal radiuses of rounded edges enough for movement of rock via spiral chutes to surface to outer dumps, with narrowing space towards bottom at level of opened level of deep portion of deposit with lesser total coefficient of opening of stage and finally board is constructed by steep vertical shelves in deep zone.
EFFECT: higher efficiency.
1 ex, 10 dwg
Authors
Dates
2005-07-20—Published
2003-12-05—Filed