FIELD: mining.
SUBSTANCE: method involves construction of working flank, drilling-and-blasting preparation of rock for excavation, excavation and transportation of rock. Working flank of pit of convex-concave shape is formed during drilling and preparation of horizon with advance. At that, frontal work advance speed on projections forms working platforms of above-lying benches with width which is bigger than adjacent below lying benches, and working platforms of below lying overburden benches are formed of the width which is bigger than that of adjacent above-lying working platforms.
EFFECT: reducing the scope of work on removal of overburden and providing maximum capacity of the pit.
2 tbl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR OPENCAST MINING OF SLOPING AND STEEP DEPOSITS OF MINERALS | 1997 |
|
RU2148713C1 |
METHOD FOR OPEN EXTRACTION OF MINERAL RESOURCE DEPOSITS | 2005 |
|
RU2304720C1 |
METHOD OF STRIP MINING OF STEEP DEPOSITS | 0 |
|
SU1155755A1 |
METHOD OF MINERAL OPENCAST MINING | 0 |
|
SU1730452A1 |
METHOD OF OPEN-PIT MINING | 1996 |
|
RU2098627C1 |
METHOD FOR OPEN PIT MINERAL MINING | 2004 |
|
RU2282721C2 |
QUARRY DEVELOPMENT METHOD | 1996 |
|
RU2118456C1 |
METHOD OF PREPARATION OF NEW HAULAGE LEVEL AND EXCAVATOR-RAILWAY COMPLEX FOR METHOD EMBODIMENT | 2000 |
|
RU2186982C1 |
DEVELOPMENT METHOD OF MINERAL RESOURCES BY SPIRAL PIT | 2010 |
|
RU2435032C1 |
METHOD FOR OPENCAST MINING OF GENTLY SLOPING AND INCLINED MINERAL DEPOSITS | 1991 |
|
RU2011827C1 |
Authors
Dates
2011-07-27—Published
2009-12-15—Filed