FIELD: building, particularly building and building structure erection, repair and renewal, for instance suitable for monuments of architecture reconstruction.
SUBSTANCE: method involves digging a ditch around foundation from both sides thereof; cleaning the foundation of soil and damaged stone; forming reinforced concrete bosses joined one to another to create reinforced concrete collar from both foundation sides; digging out ground from under foundation bottom and arranging reinforced concrete cross-piece under the foundation bottom, wherein the bridge is formed as a single whole with the bosses. The cross-piece and the bosses are reinforced with pre-stressed reinforcement arranged in the cross-piece and the bosses. Upper reinforcement ends are secured to rigid consoles installed on the bosses at foundation edges to transmit prestressing force to building structure members.
EFFECT: increased foundation reliability, service life and load-bearing capacity.
4 cl, 3 dwg
Title | Year | Author | Number |
---|---|---|---|
BANK-PROTECTING FACILITY | 2000 |
|
RU2204649C2 |
DEVICE FOR CONNECTING PRE-CAST REINFORCED CONCRETE COLUMN TO SEPARATE FOUNDATION | 2008 |
|
RU2369691C1 |
DEVICE FOR SHORING FOUNDATION SUPPORTING PART IN RAISING UNIDIRECTIONAL MOMENTARY LOAD | 1999 |
|
RU2167240C2 |
METHOD TO REINFORCE BRICKWORK PILLARS AND THEIR COLUMNAR FOUNDATIONS | 2015 |
|
RU2600473C1 |
METHOD OF REINFORCEMENT OF STRIP FOUNDATION | 1997 |
|
RU2130996C1 |
METHOD OF ERECTION OF SLAB REINFORCED CONCRETE FOUNDATION | 2018 |
|
RU2692396C1 |
ANTI-HEAVING FOUNDATION OF BUILDING WITH BASEMENT | 2010 |
|
RU2440464C1 |
METHOD OF RECONSTRUCTION OF THE STONE BUILDING | 2017 |
|
RU2668888C1 |
METHOD TO ERECT UNDERGROUND STRUCTURES BY "WALL IN SOIL" METHOD AND WALL IN SOIL ERECTED BY THIS METHOD | 2011 |
|
RU2465401C1 |
Authors
Dates
2006-01-27—Published
2004-08-02—Filed