FIELD: mechanical engineering; repair of load beams.
SUBSTANCE: proposed method includes removal of worn out part of load beam with possibility of preservation of its upper chord with all ties. New part of load beam is fitted in cutout and is welded to remaining part of beam. Moreover, new part of beam is reinforced by cover plates made of sheets with rounded off edges. Said cover plates are installed and welded to both sides of wall of remaining part of beam and its new part.
EFFECT: enlarged technological capabilities, reduced labor input at repairing, preservation of geometrical parameters of crane bridge.
2 cl 1 ex, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF RECONDITIONING CRANE RUNWAY BEAMS WITH FATIGUE CRACKS | 1998 |
|
RU2196721C2 |
METHOD OF REPAIRING CRANE-RUNWAY GIRDER | 0 |
|
SU1542767A1 |
METHOD OF REPARING CRANE GIRDERS | 0 |
|
SU1333522A1 |
REHABILITATION METHOD OF WELDING CRANE BEAM DAMAGED WITH FATIGUE CRACKS | 2009 |
|
RU2460621C2 |
METHOD OF REDUCING THE SERVICE LIFE OF THE EMERGENCY RUNWAY BEAMS | 2014 |
|
RU2583116C2 |
METHOD OF REPAIRING LOWER BOOM OF TRAVELLING-CRANE MAIN BEAM | 1998 |
|
RU2146991C1 |
CRANE RAIL STRUCTURE | 1998 |
|
RU2183186C2 |
CRANE GIRDER | 2011 |
|
RU2478557C2 |
CRANE RUNWAY STRENGTHENING METHOD | 1994 |
|
RU2114045C1 |
METAL CRANE RUNWAY STRUCTURE | 1992 |
|
RU2095527C1 |
Authors
Dates
2006-07-20—Published
2004-12-21—Filed