METHOD OF ERECTION OF ARMCO PILE-INJECTOR Russian patent published in 2008 - IPC E02D5/46 

Abstract RU 2332540 C2

FIELD: construction.

SUBSTANCE: invention relates to construction, in particular to methods of erection of piles and can be used in industrial and civil construction. The method of erection of the Armco pile-injector, including well-drilling, the reinforcement of boreholes by simultaneous installation of a reinforced-body, with an injection tube fixed in it, concreting of a trunk of the pile shaft throughout the entire height of the borehole, injection of a strengthening solution by a pulsing stream under the lower end of the pile with the unhardened concrete of the pile trunk. The reinforcing of borehole is achieved by simultaneous installation of the reinforced-body with a tube fixed in it and by an additional injection tube, through one of which the strengthening solution is delivered up to its output from the mouth of the borehole with unhardened concrete of the pile shaft, and through the second tube the strengthening solution is delivered after the hardening of concrete of the pile shaft. The injection tube which is meant for the delivery of the strengthening concrete solution for the pile shaft before it hardens, is located higher than the bottom of the well by (0.3-1) of its diameter, and the injection tube meant for delivering the strengthening solution on to the ground base after the hardening of concrete of the pile shaft, is located on the level of the bottom of the well or lower it till twice the borehole diameter. The composition of the strengthening solution delivered before the hardening of the concrete, is selected for improving the quality of concrete, while the composition of the strengthening solution delivered after the hardening of the concrete is selected for the improvement of the properties of the ground.

EFFECT: increase in the bearing capacity of Armco pile-injectors.

3 cl, 1 dwg

Similar patents RU2332540C2

Title Year Author Number
METHOD FOR BORED INJECTION PILE ERECTION 2003
  • Grin'Ko S.G.
  • Kovalev S.V.
  • Kozakov Ju.N.
  • Bulankin N.F.
RU2260093C2
METHOD FOR ERECTION OF BORED PILE 2007
  • Bulankin Nikolaj Fedorovich
RU2364683C2
ERECTION METHOD OF PILE FOUNDATION FOR REINFORCEMENT 2015
  • Sakharova Inna Dmitrievna
  • Kazarjan Vilgelm Jurevich
RU2603314C1
METHOD TO ERECT COMBINED PILE AND ITS DESIGN 2011
  • Kharisov Il'Nur Zjamilevich
  • Babich Dmitrij Sergeevich
  • Latypov Ruslan Rasulovich
RU2486315C2
METHOD FOR BORED AND CAST-IN-PLACE PILE FORMING ALONG WITH GROUND COMPACTION AT HOLE BOTTOM 2003
  • Jushchube S.V.
  • Nujkin S.S.
RU2260654C1
METHOD FOR CONSTRUCTING DRILLED PILE IN PERMAFROST SOIL 2023
  • Popsuenko Ivan Konstantinovich
  • Alekseev Andrei Grigorevich
  • Zorin Dmitrii Vasilevich
RU2803751C1
INJECTION PILE AND THE METHOD FOR ITS INSTALLATION 2021
  • Maltsev Nikolaj Sergeevich
  • Dobrynskij Andrej Vladimirovich
  • Chistyakov Dmitrij Yurevich
RU2771363C1
BORED PILE MANUFACTURING METHOD 2019
  • Popsuenko Ivan Konstantinovich
RU2706848C1
METHOD FOR INJECTION PILE BUILDING (VARIANTS) 2004
  • Polishchuk A.I.
  • Petukhov A.A.
  • Nujkin S.S.
RU2263745C1
METHOD OF INJECTION PILE BUILDING 2003
  • Polishchuk A.I.
  • Gerasimov O.V.
  • Petukhov A.A.
  • Andrienko Ju.B.
  • Nujkin S.S.
RU2238366C1

RU 2 332 540 C2

Authors

Bulankin Nikolaj Fedorovich

Dates

2008-08-27Published

2006-08-08Filed