METHOD FOR WELL REPAIR Russian patent published in 2009 - IPC E21B29/10 E21B33/13 

Abstract RU 2354804 C1

FIELD: oil and gas industry.

SUBSTANCE: invention is related to oil industry and may find application in well repair. According to method, pipe string is lowered in well. Pipe string bottom is lowered to the depth that is 20-30 m below interval of detected violation of casing pipe. Minimum circulation of liquid is created through pipe string and well tube space. Liquid outlet from tube space is sent to ditch system. Back pressure of 3-4 MPa is established at wellhead by closure of valve at the outlet from tube space. Cement mortar is pumped through casing string with its discharge from casing string bottom to interval of violation. Casing string is lifted, and its bottom is installed by 20-40 m higher than interval of violation, gate valve is closed at the outlet from well annular space, and cement grout is pushed into interval of violation in design volume. Pipes shoe is lifted to the height where it is planned to install head of cement bridge, and excess cement mortar is removed by return circulation of liquid in annular space and pipe string. Pipe string is lifted or completely withdrawn. Technological exposure is performed for cement hardening. Depth of cement sleeve location is identified. Casing string is pressurised. Cement sleeve is drilled down to interval by 5-10 m below interval of violation. Repeated pressurisation of casing string is carried out. In case of string tightness, cement sleeve is completely drilled. In case of insufficient tightness of casing string, which as a rule occurs after quite considerable violations, repeated sealing of violation is carried out.

EFFECT: increased reliability of well casing pipe repair.

1 ex

Similar patents RU2354804C1

Title Year Author Number
WELL REPAIR METHOD 2012
  • Makhmutov Il'Gizar Khasimovich
  • Zijatdinov Radik Zjauzjatovich
  • Zhirkeev Aleksandr Sergeevich
  • Tarasova Rimma Nazipovna
  • Sulejmanov Farid Bashirovich
RU2498045C1
INJECTION WELL REPAIR METHOD 2007
  • Ibragimov Nail' Gabdulbarievich
  • Taziev Mirgazijan Zakievich
  • Zakirov Ajrat Fikusovich
  • Nikitin Vasilij Nikolaevich
  • Tabashnikov Roman Alekseevich
RU2323324C1
METHOD OF PHYSICAL ABANDONMENT OF WELLS 2014
  • Makarov Dmitrij Nikolaevich
  • Farrakhov Ruslan Mansurovich
  • Muradov Rasim Alievich
  • Tukhvatullin Ramil Ravilevich
RU2576422C1
METHOD FOR WELL REPAIR 2009
  • Khisamov Rais Salikhovich
  • Ibragimov Nail' Gabdulbarievich
  • Mitchell Richard Kurt
  • Fajzullin Il'Fat Nagimovich
RU2398092C1
WELL REPAIR METHOD 2004
  • Ibragimov Nail' Gabdulbarievich
  • Zakirov Ajrat Fikusovich
  • Nikitin Vasilij Nikolaevich
  • Ozheredov Evgenij Vital'Evich
RU2280754C1
ISOLATION METHOD FOR BOREHOLE ANNULUS CIRCULATION OF SUPERIOR NON PERFORATED AQUIFER IN DOWNSTREAM PERFORATED OIL-BEARING LAYER 2015
  • Salikhov Mirsaev Mirgazjamovich
  • Galiev Ajdar Bulatisovich
RU2584256C1
METHOD OF SECONDARY CEMENTING OF PROCESS WELL OF UNDERGROUND RESERVOIRS OF VARIOUS PURPOSE 2012
  • Pyshkov Nikolaj Nikolaevich
  • Kazarjan Varazdat Amajakovich
  • Samolaeva Tat'Jana Nikolaevna
  • Dubov Nikolaj Matveevich
  • Sazonov Aleksej Alekseevich
RU2485283C1
METHOD OF PRODUCTION STRING SEALING 2017
  • Zhirkeev Aleksandr Sergeevich
  • Sakhapova Alfiya Kamilevna
  • Khamidullina Elvina Rinatovna
  • Khasanova Dilbarkhon Kelamedinovna
RU2669650C1
INSULATION METHOD FOR BEHIND-THE-CASING FLOWS IN PRODUCTION WELL 2020
  • Ziiatdinov Radik Ziauziatovich
RU2739181C1
METHOD OF REDUCING WELL REPAIR DURATION WITH INSTALLATION OF THE FLEXIBLE PIPE 2017
  • Ksenofontov Denis Valentinovich
  • Novikov Igor Mikhajlovich
  • Minapov Ravil Ramilevich
  • Sabanov Aleksej Vasilevich
  • Paskidov Andrej Alekseevich
RU2670795C9

RU 2 354 804 C1

Authors

Ibragimov Nail' Gabdulbarievich

Taziev Mirgazijan Zakievich

Zakirov Ajrat Fikusovich

Nikitin Vasilij Nikolaevich

Tabashnikov Roman Alekseevich

Asljamov Ajdar Ingelevich

Dates

2009-05-10Published

2008-06-07Filed