FIELD: mining.
SUBSTANCE: invention refers to mining and can be implemented at development of flat dipping beds of minerals, mainly coal beds, in cleared pit walls and in places of bed exposure. Mining of the bed of mineral is performed by means of complex of deep development of beds - CDDB - of mining chambers. Transporting mineral from mining chambers to surface is carried out via a box multi-link transporter. Massifs of mineral are left between mining chambers. Places of location and amplitudes of disjunctive geological disturbances of uplift type are determined within the ranges of the mined region of the mineral bed. The mining chambers are parallel to fractures of impenetrable disjunctive geological disturbances. Massifs of useful mineral are left under fractures of disjunctive geological disturbances. Disturbances with amplitudes of vertical upheaval of the bed bigger, than their maximum permissible values, are considered as impenetrable disjunctive geological disturbances. Transfer of CDDB at such disturbances is impossible because of dangerous bends in a vertical plane of the box multi-link transporter causing deformation and destruction of the transporter. Maximum permissible values of amplitudes of vertical upheaval of the bed are accepted as not exceeding product of distance from the beginning of the mining chamber to the disjunctive geological disturbance by tangent of maximum permissible value of an angle between the plane of a working platform, whereon CDDB is mounted, and the box multi-link transporter; when the product is exceeded, deformation and destruction of the box multi-link transporter occur.
EFFECT: increased efficiency with implementation of CDDB and reduced production costs and losses of mineral.
1 ex, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF OPEN-UNDEGROUND MINING OF COAL BEDS | 2007 |
|
RU2342532C1 |
METHOD FOR OPEN-UNDERGROUND DEVELOPMENT OF FLAT-LYING FORMATIONS | 2019 |
|
RU2715503C1 |
UNDERGROUND MINERAL MINING METHOD | 2005 |
|
RU2305188C2 |
UNDERGROUND MINING OF A COAL SEAM | 2022 |
|
RU2805222C1 |
METHOD OF OPEN-UNDERGROUND EXTRACTION OF COAL PILLARS LEFT BETWEEN MINE-FILED BOUNDARY AND PIT WALL | 2007 |
|
RU2329380C1 |
METHOD FOR EXTRACTION OF MINERAL RESOURCES | 2003 |
|
RU2247241C1 |
METHOD FOR COMBINED DEVELOPMENT OF GENTLY PITCHING COAL BEDS | 2014 |
|
RU2600579C2 |
SUBSURFACE WORKING OF CHITTERS AT HIGH GAS CONTENT OF COAL AND HOST ROCK | 2013 |
|
RU2516088C1 |
PROCESS OF DEVELOPMENT OF THICK GENTLY DIPPING COAL SEAMS | 2002 |
|
RU2224108C2 |
METHOD OF MINERAL EXTRACTION IN FILLED FLANKS OF OPENCAST | 2001 |
|
RU2205955C1 |
Authors
Dates
2009-05-27—Published
2008-01-28—Filed