FIELD: construction, road engineering.
SUBSTANCE: invention relates to the field of earth works production in stripping works, digging pits and trenches under permafrost soil condition. The method to prepare permafrost soil for development is realised by water distribution along the surface of the unfrozen section. At the same time after natural thawing of soil to the depth of 0.15-0.20 m the thawed soil is removed, to form a "trough", and running water is sent into it along the surface of the frozen section with a flow rate of 5-10 l/m2 of the surface per hour. At the same time preparation of permafrost soil is carried out in summer period at the air temperature of more than 0°C and water temperature of at least +1°C.
EFFECT: higher efficiency of permafrost soils unfreezing.
2 cl
Title | Year | Author | Number |
---|---|---|---|
METHOD OF MELTING OF FROZEN ROCKS AND SOIL | 2015 |
|
RU2602460C1 |
METHOD FOR ERECTING EMBANKMENT FROM SUBSTANDARD SOILS ON PERMAFROST | 2016 |
|
RU2647517C1 |
METHOD FOR EXCAVATION OF FROZEN GROUND | 1989 |
|
RU2009299C1 |
METHOD FOR LOCAL DEFROSTING OF PERMAFROST GROUND | 2003 |
|
RU2236507C1 |
METHOD FOR ERECTION OF EMBANKMENT ON FROZEN SOILS | 2008 |
|
RU2378446C2 |
METHOD OF EXTRACTING HIGH TEMPERATURE WATER FROM SILT-DETENTION WATER RESERVOIRS (VERSIONS) | 2019 |
|
RU2723315C1 |
FROZEN SOIL WORKING METHOD | 0 |
|
SU885559A1 |
METHOD OF STOPPING FIRE IN STEPPE FIRES AND PREVENTING PEAT FIRES | 2019 |
|
RU2705611C1 |
CATCHING CANAL | 0 |
|
SU1073370A1 |
PROCESS OF DEVELOPMENT OF FROZEN GROUND BY SUCTION-TUBE DREDGE | 2001 |
|
RU2204658C2 |
Authors
Dates
2012-04-27—Published
2010-12-08—Filed