FIELD: machine building.
SUBSTANCE: invention refers to construction of pipelines in water-flooded and marshy areas of the route. Method involves excavation of a trench, laying of pipeline into the trench, covering of itself, bottom, side surfaces and berms of trench with flexible mats so that side pockets are formed, filling of the above said and top of pipeline with soil, covering of soil with longitudinal sections of mats and final filling of the trench so that external bead is formed. One of the two side pockets of each mat is made so that it is deflected above the trench bottom. Pockets with deflection are arranged at adjacent unfolded mats in a staggered order relative to pipeline axis. At that, each mat on the side of deflected pocket is fixed against being displaced on the berm of trench with banked ground, and then, opposite pocket is filled up to the top of pipeline, thus preventing the displacement of mat on its surface by partial filling of deflected pocket, and after that, its filling and filling of the trench as a whole is continued. Design length of the mat section forming the deflected pocket is determined depending on elasticity modulus and strength at tension of mat material (geotextile cloth).
EFFECT: reliable fastening of pipeline in conditions of water-flooded soil without additional labour costs and material consumption.
2 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD TO INSTALL UNDERGROUND PIPELINE | 2011 |
|
RU2455551C1 |
METHOD FOR LAYING SUBSURFACE PIPELINE | 2013 |
|
RU2521521C1 |
METHOD LAYING UNDERGROUND PIPE LINE | 1995 |
|
RU2090795C1 |
METHOD AND DEVICE FOR LAYING PIPELINE | 2005 |
|
RU2274793C1 |
METHOD OF LAYING PIPE LINES (VERSIONS) AND DEVICE FOR REALIZATION OF THIS METHOD | 2004 |
|
RU2244191C1 |
METHOD OF BALLASTING SUBTERRANEAN PIPE LINE | 1998 |
|
RU2153119C2 |
METHOD OF PIPELINE REPAIR | 1999 |
|
RU2180718C2 |
METHOD FOR ERECTION OF PIPELINE IN FROZEN AND WATERLOGGED SOIL | 2010 |
|
RU2452886C2 |
DEVICE FOR INCREASING DEAD LOAD OF PIPE LINE AND METHOD OF ITS BALLASTING | 1992 |
|
RU2047035C1 |
METHOD OF LAYING UNDERGROUND PIPELINE | 0 |
|
SU1268860A1 |
Authors
Dates
2012-11-20—Published
2011-05-16—Filed