FIELD: construction.
SUBSTANCE: device for reinforcement of ceiling with wooden beams includes metal beams along its whole length, mounted in the gaps between wooden beams. Bottom point of metal beams is located below the top of wooden beams with total inner dimension of the rest of ceiling. At metal beam top, a top rod band passing through a wooden beam and connected by supports with lower rod band is mounted, with the wooden beam resting on lower rod band over supporting plates.
EFFECT: enhanced structural capability of ceiling under reconstruction.
2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR REINFORCING CEILING WITH WOODEN BEAMS, REINFORCED CEILING | 1996 |
|
RU2120008C1 |
METHOD FOR RECONSTRUCTION OF RESIDENTIAL BUILDINGS WITH WOODEN INTERMEDIATE FLOORS | 2019 |
|
RU2708289C1 |
METHOD FOR CONSTRUCTING BUILDING ADDITION | 2010 |
|
RU2442868C1 |
METHOD TO REINFORCE STONE FLOOR VAULTS OF BUILDING | 2011 |
|
RU2471943C2 |
LARGE-SPAN SPATIAL SYSTEM OF BUILDING COVER | 2012 |
|
RU2502851C1 |
METHOD FOR ADDITIONAL RESIDENTIAL BUILDING STORY ERECTION | 2006 |
|
RU2308586C1 |
BEARING STRUCTURE OF MULTISTOREY BUILDING STRUCTURE (VERSIONS) AND METHOD OF ERECTION OF MULTISTOREY LONG SPAN STRUCTURE | 2015 |
|
RU2596228C1 |
METHOD TO ERECT ADDITIONAL STORIES FOR BUILDING RECONSTRUCTION | 2006 |
|
RU2312960C1 |
BUILDING COVERING RECONSTRUCTION METHOD | 2006 |
|
RU2340738C2 |
METHOD OF STRENGTHENING STONE VAULTED FLOORINGS OF BUILDING | 2016 |
|
RU2640612C2 |
Authors
Dates
2014-01-20—Published
2012-07-03—Filed