FIELD: mining.
SUBSTANCE: formations are excavated in inverse order in a panel with aligned arrangement of chambers and pillars. Meanwhile the thinner formation is excavated by chamber-and-pillar system with regular cutting of inter-chamber belt pillars by break-throughs towards the front of pillar mining, meanwhile a ventilation of a working zone and dust air removal is performed due to mine ventilating pressure drop through the last inter-chamber break-through, and the thicker formation is excavated by chambered system with lagging from the thinner formation.
EFFECT: improvement of performance of excavation of thinner formations due to increase of extraction of minerals from subsoil by regular cutting of interchamber pillars and ensuring of efficient ventilation and dust removal from a working zone of operators of winning machines and self-propelled transportation equipment into excavated space.
2 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR CHAMBER MINING WHEN PREPARING HORIZONS | 2016 |
|
RU2627803C1 |
METHOD FOR PREPARATION OF EXCAVATION SITE AT CHAMBER DEVELOPMENT SYSTEM | 2015 |
|
RU2577570C1 |
TREATMENT OF POTASH SEAMS | 2013 |
|
RU2538016C1 |
METHOD OF SLANT COAL SEAMS DEVELOPMENT | 1994 |
|
RU2068498C1 |
METHOD OF PREPARATION AND MINING CONTIGUOUS FLAT SEAMS | 2013 |
|
RU2530102C1 |
LAYERED ROOM-AND-PILLAR SYSTEM WITH COMPLETE STOWING | 2011 |
|
RU2486340C2 |
METHOD FOR SECONDARY TREATMENT OF SALT BED | 2011 |
|
RU2468206C1 |
METHOD OF CHAMBERS VENTILATION IN MINING THICK BED BY CHAMBER SYSTEM | 2000 |
|
RU2183274C1 |
EXCAVATION METHOD OF THICK FLAT-LYING COAL SEAM WITH FAST ROOF | 2006 |
|
RU2327037C1 |
METHOD FOR HANDLING COAL LAYERS BY MEANS OF CHAMBER-COLUMNAR SYSTEM | 2003 |
|
RU2229598C1 |
Authors
Dates
2014-11-20—Published
2013-08-27—Filed